Field settings
ESIE04-01
4–18
Part 4 – Commissioning and Test Run
3
1
4
5
2.9
Setting the Centralized Group No.
When?
If you want to carry out centralized control with a central remote controller and a unified ON/OFF
controller, you have to set the group No. for each group with the remote controller.
Wired remote
controller
The illustration below shows the wired remote controller.
Setting
To set the “Centralized group No.”, proceed as follows:
SETTING
UNIT No.
GROUP
3
1
4
5
6
2
7
Unit N°
First Code N°
Second Code N°
Mode N°
Field set mode
Step
Action
1
Switch ON the power supply of the central remote controller, the unified ON/OFF control-
ler and the indoor unit(s).
2
Hold down the INSPECTION/TEST button for at least 4 s during normal mode to enter
the “Field setting mode”.
3
Press the TEMPERATURE CONTROL button until “Mode No.” “
00
” appears.
4
Press the INSPECTION/TEST button to inspect the group No. display.
5
Set the “Group No.” for each group by pressing the PROGRAMMING TIME button.
The “Group No.” rises in the order of 1—00, 1—01, ..., 1—15, 2—00, ..., 2—15, 3—00,
etc.
The unified ON/OFF controller however displays only the range of group numbers
selected by the switch for setting each address.
6
Press the CONFIRMATION button to enter the selected group No.
7
Press the INSPECTION/TEST button to return to normal mode.
RZQ - Final.book Page 18 Wednesday, September 8, 2004 8:40 AM
Summary of Contents for RZQ71~125B7V3B
Page 1: ...Service Manual ESIE04 01 RZQ71 125B7V3B Sky Air Inverter R 410A B series ...
Page 2: ......
Page 24: ...ESIE04 01 1 2 Part 1 System Outline 3 1 1 5 ...
Page 32: ...General Outline Outdoor Units ESIE04 01 1 10 Part 1 System Outline 3 1 1 4 5 ...
Page 64: ...General Outline Indoor Units ESIE04 01 1 42 Part 1 System Outline 3 1 1 4 5 ...
Page 76: ...Specifications ESIE04 01 1 54 Part 1 System Outline 3 1 1 4 5 ...
Page 92: ...Functional Diagrams ESIE04 01 1 70 Part 1 System Outline 3 1 1 4 5 ...
Page 94: ...ESIE04 01 1 72 Part 1 System Outline ...
Page 122: ...Wiring Diagrams ESIE04 01 1 100 Part 1 System Outline 3 1 1 4 5 ...
Page 140: ...ESIE04 01 2 2 Part 2 Functional Description 3 1 2 5 ...
Page 162: ...General Functionality ESIE04 01 2 24 Part 2 Functional Description 3 1 2 4 5 ...
Page 200: ...Outdoor Unit Functional Concept ESIE04 01 2 62 Part 2 Functional Description 3 1 2 4 5 ...
Page 202: ...ESIE04 01 3 2 Part 3 Troubleshooting 3 1 3 5 ...
Page 288: ...Error Codes Outdoor Units ESIE04 01 3 88 Part 3 Troubleshooting 3 1 3 4 5 ...
Page 312: ...Additional Checks for Troubleshooting ESIE04 01 3 112 Part 3 Troubleshooting 3 1 3 4 5 ...
Page 314: ...ESIE04 01 4 2 Part 4 Commissioning and Test Run 3 1 4 5 ...
Page 356: ...ESIE04 01 5 2 Part 5 Disassembly and Maintenance 3 1 5 ...
Page 484: ...ESIE04 01 viii Index 3 1 4 5 ...