Ambient temperature
Humidity
Minimum thickness
≤30°C
75% to 80% RH
15 mm
>30°C
≥80% RH
20 mm
6.4 Preparing electrical wiring
6.4.1 About preparing electrical wiring
INFORMATION
Also read the precautions and requirements in the
7].
INFORMATION
"7.7.5 Specifications of standard wiring components"
WARNING
▪
If the power supply has a missing or wrong N-phase, equipment might break
down.
▪
Establish proper earthing. Do NOT earth the unit to a utility pipe, surge absorber,
or telephone earth. Incomplete earthing may cause electrical shock.
▪
Install the required fuses or circuit breakers.
▪
Secure the electrical wiring with cable ties so that the cables do NOT come in
contact with sharp edges or piping, particularly on the high-pressure side.
▪
Do NOT use taped wires, stranded conductor wires, extension cords, or
connections from a star system. They can cause overheating, electrical shock or
fire.
▪
Do NOT install a phase advancing capacitor, because this unit is equipped with an
inverter. A phase advancing capacitor will reduce performance and may cause
accidents.
WARNING
▪
All wiring MUST be performed by an authorised electrician and MUST comply
with the applicable legislation.
▪
Make electrical connections to the fixed wiring.
▪
All components procured on-site and all electrical construction MUST comply
with the applicable legislation.
WARNING
ALWAYS use multicore cable for power supply cables.