TRIAL OPERATION AND TESTING

(1) Measure the supply voltage and make sure that it falls in the specified range.
(2) Trial operation should be carried out in either cooling or heating mode.

„

„

„

„

For Heat pump.
In cooling mode, select the lowest programmable temperature; in heating mode, select the highest programmable temperature.

• Trial operation may be disabled in either mode depending on the room temperature.
• After trial operation is complete, set the temperature to a normal level (26°C to 28°C in cooling mode, 20°C to 24°C in 

heating mode).

• For protection, the system disables restart operation for 3 minutes after it is turned off.

„

„

„

„

For Cooling only.
Select the lowest programmable temperature.

• Trial operation in cooling mode may be disabled depending on the room temperature.

Use the remote control for trial operation as described below.

• After trial operation is complete, set the temperature to a normal level (26

°

C to 28

°

C).

• For protection, the unit disables restart operation for 3 minutes after it is turned off.

(3) Carry out the test operation in accordance with the Operation Manual to ensure that all functions and parts, are working 

properly.
* The air conditioner requires a small amount of power in its standby mode.  If the system is not to be used for some time after 

installation, shut off the circuit breaker to eliminate unnecessary power consumption.

* If the circuit breaker trips to shut off the power to the air conditioner, the system will restore the original operation mode when 

the circuit breaker is turned on again.

Trial operation and testing

(1) Press ON/OFF button to turn on the system.

(2) Simultaneously press center of TEMP button and MODE button.

(3) Press MODE button twice.

  (“ ” will appear on the display to indicate that Trial Operation mode is selected.)

(4) Trial run mode terminates in approx. 30 minutes and switches into normal mode. To quit a trial operation, press

ON/OFF button.

Trial operation from remote controller

Test items

Check

Symptom

(diagnostic display on RC)

Test items

Indoor and outdoor units are installed properly on solid bases.
No refrigerant gas leaks.

Refrigerant gas and liquid pipes and indoor drain hose
extension are thermally insulated.
Draining line is properly installed.
System is properly earthed.
The specified wires are used for interconnecting wire
connections.
Indoor or outdoor unit’s air inlet or discharge has clear path of air.
Shut-off valves are opened.
Indoor unit properly receives remote controller commands.

Fall, vibration, noise
Incomplete cooling/heating
function
Water leakage

Water leakage
Electrical leakage
Inoperative or burn damage

Incomplete cooling/heating
function
Inoperative

01_EN_3P132003-3K.fm  Page 11  Wednesday, September 28, 2005  3:32 PM

Summary of Contents for Super Multi NX FDKS25EAVMB

Page 1: ...s Espa ol Italiano Portugues T rk e Installation manual R410A Split series Installationsanleitung Split Baureihe R410A Manuel d installation S rie split R410A Montagehandleiding R410A Split systeem Ma...

Page 2: ...5 74736 KRQ EMC97 4957 Daikin TCF 015 74736 KRQ EMC97 4957 Daikin TCF 015 74736 KRQ EMC97 4957 Daikin TCF 015 74736 KRQ EMC97 4957 Daikin TCF 015 74736 KRQ EMC97 4957 Daikin TCF 015 74736 KRQ EMC97 49...

Page 3: ...r installation may cause terminal overheating electrical shock or fire When installing or relocating the system be sure to keep the refrigerant circuit free from substances other than the specified re...

Page 4: ...conditions under which the electric wave is generated even if a one meter allowance is maintained Use suspension bolts to install the unit Check whether or not the ceiling is strong enough to support...

Page 5: ...ontrol box and drain pump are easy Install the inspection opening also in the lower part of the unit Make sure the range of the unit s external static pressure is not exceeded See the technical docume...

Page 6: ...re not covered by anti sweat material Make sure there are no gaps between the different pieces of sealing pad 4 Attach the hanger right insulation to the right hanger Stored in outlet vent See the bel...

Page 7: ...the unit to the surface of the water at both ends of the plastic tube and adjust the unit horizontally One thing to watch out for in particular is if it is installed so that the slope is not in the d...

Page 8: ...ent gas leakage apply refrigeration machine oil on both inner and outer surfaces of the flare Use refrigeration oil for R410A 2 Align the centres of both flares and tighten the flare nuts 3 or 4 turns...

Page 9: ...refrigerant piping the unit piping and branch piping must be further reinforced Reinforce the insulation when installing the unit near bathrooms kitchens and other similar locations Refer to the follo...

Page 10: ...ere causing water to leak Drain piping passing indoors Drain sockets Referring the figure below insulate the metal clamp and drain hose using the included large sealing pad PRECAUTIONS Drain piping co...

Page 11: ...ncy is at least 50 in a gravimetric technique Outlet side Connect the duct according to the inside of the outlet side flange Wrap the outlet side flange and the duct connection area with aluminum tape...

Page 12: ...rough the wiring through hole and connect to the power wiring terminal block 4P Be sure to put the part of the sheathed vinyl into the control box Warning Do not use tapped wires stand wires extension...

Page 13: ...If the system is not to be used for some time after installation shut off the circuit breaker to eliminate unnecessary power consumption If the circuit breaker trips to shut off the power to the air...

Page 14: ...0511 HT 3P132003 3K M05B026A...

Reviews: