Test Operation
Si39-502A
88
Test Operation
1.
Test Operation
1.1
Procedure and Outline
Follow the following procedure to conduct the initial test operation after installation.
1.1.1 Check Work Prior to Turn Power Supply On
Check on refrigerant piping /
insulation materials.
Check airtight test and vacuum
drying.
Check on amount of refrigerant
charge.
Check the stop valves for
conditions.
Terminal
Dryer
(1000W)
Check the below items.
2
Power wiring
2
Control transmission wiring
between units
2
Earth wire
¡
Is the wiring performed as specified?
¡
Is the designated wire used?
¡
Is the wiring screw of wiring not loose?
¡
Is the grounding work completed?
¡
Is the insulation of the main power supply circuit deteriorated?
Use a 500V megger tester to measure the insulation. (*1)
2
Do not use a megger tester for other circuits than 200V (or
240V) circuit.
*1:Measure to be taken against decreased insulation resistance in
the compressor
If the compressor is left to stand for
an extended period of time after the
refrigerant charge with the stop valve
open and the power supply OFF, the
refrigerant may be mixed in the
compressor, thus decreasing the
insulation resistance.
Heat the compressor as shown on
the right and then recheck the
insulation.
¡
Is the pipe size proper?
¡
Is the pipe insulation material installed securely?
Liquid and gas pipes need to be insulated. (Otherwise causes
water leak.)
¡
Have the airtight test and the vacuum drying been conducted
according to the procedure in the Installation Manual?
¡
Has a proper amount of refrigerant been charged according to the
result of the "Calculation of the refrigerant additional charging
amount"?
Charge refrigerant in the liquid state from the service port of the
liquid-side stop valve, with stopping the outdoor unit after the
completion of vacuuming.
If the total amount of refrigerant calculated cannot be charged,
follow information in "Additional charging of refrigerant" on the
following page to charge the refrigerant by the deficient amount.
¡
Has the refrigerant additional charging amount been recorded on
the "Service Precautions" label?
¡
Check to be sure the stop valves are under the following
conditions.
Liquid-side stop valve
Open
Gas-side stop valve
Open
Summary of Contents for VRV II RXYQ8MY1K
Page 53: ...Specifications Si39 502A 42 Specifications...
Page 143: ...Field Setting Si39 502A 132 Test Operation...
Page 258: ...Si39 502A Wiring Diagrams for Reference Appendix 247 FXCQ40M 50M 80M 125MVE 3D039557A...
Page 260: ...Si39 502A Wiring Diagrams for Reference Appendix 249 FXKQ25M 32M 40M 63MVE 3D039564A...
Page 264: ...Si39 502A Wiring Diagrams for Reference Appendix 253 FXMQ40M 50M 63M 80M 100M 125MVE 3D039620A...
Page 265: ...Wiring Diagrams for Reference Si39 502A 254 Appendix FXMQ200M 250MVE 3D039621A...
Page 266: ...Si39 502A Wiring Diagrams for Reference Appendix 255 FXHQ32M 63M 100MVE 3D039801C...
Page 267: ...Wiring Diagrams for Reference Si39 502A 256 Appendix FXAQ20M 25M 32M 40M 50M 63MVE 3D034206A...
Page 269: ...Wiring Diagrams for Reference Si39 502A 258 Appendix FXUQ71M 100M 125MV1 3D044973...
Page 270: ...Si39 502A Wiring Diagrams for Reference Appendix 259 FXAQ20MH 25MH 32MH 40MH 50MHV1 3D046348A...
Page 271: ...Wiring Diagrams for Reference Si39 502A 260 Appendix FXLQ20MH 25MH 32MH 40MH 50MHV1 3D046787A...
Page 272: ...Si39 502A Wiring Diagrams for Reference Appendix 261 BEVQ50MVE 3D046579A Notes...
Page 273: ...Wiring Diagrams for Reference Si39 502A 262 Appendix BEVQ71M 100M 125MVE 3D044901A Notes...
Page 285: ...Piping Installation Point Si39 502A 274 Appendix...
Page 293: ...Method of Replacing The Inverter s Power Transistors and Diode Modules Si39 502A 282 Appendix...
Page 307: ...Si39 502A iv Index...