Components
Service manual
217
REYQ8~20+REMQ5U7Y1B
VRV IV+ Heat Recovery
ESIE18-15B – 2020.05
BS4~16Q-A
a
a
Fuse
Blown fuse on the Branch selector box
PCB?
Action
Yes
Replace the blown fuse, see
345].
No
Return to
342] of the Branch
selector box PCB and continue with the
next procedure.
To check the DIP switches of the branch selector box PCB
1
To check the correct position of the DIP switches, refer to the Installation
manual. Correct as needed.
Is the problem solved?
Action
Yes
No further actions required.
No
Return to
214] of the Branch
selector box PCB and continue with the
next procedure.
Problem solved?
After all checking procedures listed above have been performed:
Is the problem solved?
Action
Yes
No further actions required.
No
Return to the troubleshooting of the
specific error and continue with the
next procedure.
3.2.2 Repair procedures
To remove the branch selector box PCB
Prerequisite:
Turn OFF the respective circuit breaker.
1
Remove the required plate work, see
2
Disconnect transmission wiring from F1/F2 terminals.