3
|
Components
Service manual
293
REYQ8~20+REMQ5U7Y1B
VRV IV+ Heat Recovery
ESIE18-15B – 2020.05
Any blown fuses on the main PCB?
Action
No
Return to
290] of the main PCB
and continue with the next procedure.
To check the varistors of the main PCB
Prerequisite:
First perform all earlier checks of the main PCB, see
290].
1
Measure the resistance of the varistor. If the reading is nearly infinite, the
varistor is still good.
a
a
a
Varistors
Any broken varistors on the main PCB? Action
Yes
Replace the main PCB, see
No
Return to
290] of the main PCB
and continue with the next procedure.
Problem solved?
After all checking procedures listed above have been performed:
Is the problem solved?
Action
Yes
No further actions required.
No
Return to the troubleshooting of the
specific error and continue with the
next procedure.
3.11.2 Repair procedures
To correct the wiring from the main power supply terminal to the main PCB
1
Correct the wiring from the main power supply terminal to the PCB, see
385].
Is the problem solved?
Action
Yes
No further actions required.
No
Return to
290] of the main PCB
and continue with the next procedure.
To remove the main PCB
Prerequisite:
Stop the unit operation via the central controller.
Summary of Contents for VRV IV+
Page 473: ......
Page 474: ......
Page 475: ......
Page 476: ...ESIE18 15B 2020 05 Copyright 2020 Daikin Verantwortung für Energie und Umwelt ...