background image

34

 

Centrifugal Chillers 

IM 1044-2 

Multiple Chiller Setup 

Single compressor chillers WSC and dual compressor chillers WDC and WCC have their main control components 
factory wired to an internal pLAN network so that the components can communicate with each other, within the 
chiller itself.  On multi-chiller applications, up to four chillers, either single, or dual compressor, can be 
interconnected by this internal pLAN. All that is required is simple field RS485 interconnecting wiring, the 
addition of accessory communication isolation board(s) 485OPDR (

Daikin

 P/N 330276202), and some MicroTech 

II control settings (see special WCC instructions at the end of this section). The 485OPDR isolation board can be 
purchased with the unit or separately, during or after chiller installation. The number of boards required equals the 
number of chillers minus one.  

Note: 

pLAN multiple chiller interconnection is designed for parallel chiller installations with the leaving water 

sensors in their normal location in the outlet nozzle.  

For two units in series operation, the leaving chilled water sensors must be moved far enough downstream from the 
last chiller to insure reading a thoroughly mixed water temperature. Passing through one or two elbows will usually 
suffice. Series chillers are normally single pass resulting in undesirable temperature stratification at the outlet nozzle 

Interconnectability 

Centrifugal models WSC and WDC of various vintages with MicroTech II controllers can be interconnected but all 
must be loaded with the most recent control software.  

Responsibilities 

Unless otherwise stated in the contract documents, the interconnecting MicroTech II pLAN RS485 multiple chiller 
wiring between chillers is the responsibility of the installing contractor and should be completed prior to startup.  

The 

Daikin

 startup technician is responsible is to check the wiring and make the appropriate control changes. 

pLAN Wiring 

Connect chillers together (pLAN, RS485 wiring) as shown in Figure 21 on the following page. The first chiller in 
the connection can be designated as Chiller A. The isolation board is attached to the DIN rail adjacent to the Chiller 
A unit controller. The isolation board has a pigtail that is plugged into J10 on the controller. Most chillers will 
already have a universal communication module (UCM) that connects the controller to the touchscreen already 
plugged onto J10. If this is the case, plug the isolation module pigtail into the empty RJ11 pLAN port on the UCM. 
This is equivalent to plugging into the unit controller directly. 

Next, interconnecting wiring is needed between Chiller A and Chiller B. 

Two Chillers

: If only two chillers are to be connected, Belden M9841 (RS 485 Spec Cable) is wired from the 

485OPDR isolation board (terminals A, B, and C) on Chiller A to the J11 port on the unit controller of Chiller B. At 
J11, the shield connects to GND, the blue/white wire to the (+) connection, and the white/blue to the (-) connection. 

Note that Chiller B does not have an isolation board. The last chiller (B in this case) to be connected does not need 
an isolation board. 

Three or Four Chillers

: If three or more chillers are to be connected, the interconnecting wiring is still made to 

Chiller B’s J11 port. The second chiller (Chiller B) must have a 485OPDR isolator board that will be plugged into 
Chiller B’s UCM pLAN port. Chiller B will look like Chiller A. 

The wiring from Chiller B to Chiller C will be the same as A to

 

B. That is, Belden cable connects from A, B, and C 

on B’s 485OPDR board to chiller C’s L11 port. Chiller C has no 485OPDR isolation board. 

The procedure is repeated to the fourth chiller if four chillers are interconnected. 

Sequencing 

The 

Daikin

 technician can set up different strategies for starting and stopping networked compressors, chillers, and 

pumps depending on site requirements. 

Summary of Contents for WSC063

Page 1: ...Maintenance Manual IM 1044 2 Centrifugal Compressor Water Chillers Group Chillers Part Number 331374801 REV 0A Date August 2012 2013 Daikin Applied Models WSC WDC WCC HSC Includes High Voltage 10 11k...

Page 2: ...57 Operator Schools 57 Warranty Statement 57 Hazard Identification DANGER Dangers indicate a hazardous situation which will result in death or serious injury if not avoided WARNING Warnings indicate p...

Page 3: ...100 113 and 126 size WDC and WCC units are available in high voltage 10 11kV These models will have different dimensions weights and installation details than the standard low medium voltage models S...

Page 4: ...on This will aid in handling the equipment Extreme care must be used when rigging the equipment to prevent damage to the control panels or refrigerant piping See the certified dimension drawings inclu...

Page 5: ...porator and condenser tubes are rolled into the tube sheets to permit replacement if necessary The length of the vessel should be allowed at one end Doors or removable wall sections can be utilized fo...

Page 6: ...the mounting slab or framework but should this be desirable 1 1 8 28 5 mm mounting holes are provided in the unit support at the four corners Note Units are shipped with refrigerant and oil valves cl...

Page 7: ...ndenser Water Temperature EXV Min ECWT 5 25 0 88 LWT DTFL PLD 100 22 PLD 100 2 ECWT Entering condenser water temperature LWT Leaving chilled water temperature DTFL Chilled Water Delta T at full load P...

Page 8: ...llers are selected for lower kW per ton the cooling tower fan motor power becomes a higher percentage of the total peak load chiller power Daikin s Energy Analyzer program can optimize the chiller tow...

Page 9: ...a 2 pass configuration and copper tubing may have an over under connection configuration on the evaporator rather than the side by side configuration shown here Consult Certified Drawings for exact c...

Page 10: ...mal dispersion flow switches are available from Daikin as a factory mounted option It is mounted in an evaporator and condenser water nozzle and factory wired A paddle type flow switch can be supplied...

Page 11: ...d to be sure that it conforms to the system design Some form of temperature control is also required if an uncontrolled tower can supply water below about 65 F 18 C If tower fan control is not adequat...

Page 12: ...ers IM 1044 2 Figure 7 Heat Recovery Schematic EVAPORATOR TOWER CONDENSER RECOVERY CONDENSER AUXILIARY HEATER HEAT LOAD TC TC COOLING LOAD OPEN CIRCUIT TOWER HEAT RECOVERY CHILLER LEGEND TC TEMPERATUR...

Page 13: ...IM 1044 2 Centrifugal Chillers 13 Field Insulation Guide Figure 8 Insulation Requirements Cooling only Units...

Page 14: ...14 Centrifugal Chillers IM 1044 2...

Page 15: ...7 6 2543 1152 478 217 148 67 1 E2012 X 37 139 84 7 8 2862 1296 478 217 148 67 1 E2209 X 38 145 66 6 1 2708 1227 600 272 175 79 1 E2212 X 45 170 90 8 3 3071 1391 600 272 175 79 1 E2216 X 79 301 144 13...

Page 16: ...alves C1809 X 597 271 43 162 1887 856 2 C1812 X 845 384 44 166 2050 930 2 C2009 X 728 330 47 147 1896 860 2 C2012 X 971 440 62 236 2528 1147 2 C2209 X 822 372 73 278 2596 1169 2 C2212 X 1183 537 76 29...

Page 17: ...8863 22007 9982 WSC087 2609 2209 651 295 10980 4981 11990 5439 12180 5525 13190 5983 WSC087 2612 2212 859 389 12309 5583 13549 6146 13509 6128 14749 6690 WSC087 2609 2609 686 311 11716 5314 12960 587...

Page 18: ...DC087 4216 4216 44470 20189 51463 23364 47204 21431 54197 24605 WDC100 113 3616 3616 41816 18967 46513 21098 See Note 2 See Note 2 WDC100 113 126 7kV 4216 4216 50470 22893 57463 26065 See Note 2 See N...

Page 19: ...water it is important that the water pressure drop across the evaporator is greater than the pressure drop across the oil cooler or insufficient oil cooler flow will result If the pressure drop across...

Page 20: ...water in the 45 F to 65 F 7 C to 18 C range considerably less water will be used and the pressure drop will be greatly reduced When supplied with city water the oil piping must discharge through a tra...

Page 21: ...COOLING TOWER OPEN DRAIN DRAIN VALVE OR PLUG SOLENOID VALVE OIL COOLER WATER SUPPLY STOP VALVE STRAINER MAX 40 MESH COOLING TOWER MAKEUP DISCHARGE ABOVE HIGHEST POSSIBLE WATER LEVEL R S Oil Reservoir...

Page 22: ...be followed Condensers have two relief valves as a set with a three way valve separating the two valves large condensers will have two such sets One valve remains active at all times and the second v...

Page 23: ...A pipe increaser must always be installed at the valve outlet Common Piping According to ASHRAE Standard 15 the pipe size cannot be less than the relief valve outlet size The discharge from more than...

Page 24: ...ian the contractor should obtain and apply the following items on medium voltage above 600 volts applications Materials required 1 Loctite brand safety solvent 12 oz package available as Daikin part n...

Page 25: ...ve to hold it in place until the terminal box is mounted The gasket must be located such that the gasket holes align with the threaded holes in the casting 2 Remove the terminal box door before liftin...

Page 26: ...ench and tighten as shown below The buss bars are factory connected to the box main power terminals and field connected to the motor terminals Use Scotch Linerless Rubber Splicing Tape to cover the co...

Page 27: ...al box power connectors are made to the landing points shown in Figure 15captive and attached with a bolt already in the connector Figure 15 Terminal Box Mounted Front View Figure 16 Terminal Box Moun...

Page 28: ...ear Temperature Sensors connect to the controller s J6 terminal strip Brown B6 White B7 Blue B8 Black Ground Motor Terminal Box to Chiller Control Panel Field wiring is required between the terminal b...

Page 29: ...1 If the unit is supplied with a factory mounted starter or VFD the control circuit power supply is factory wired from a transformer located in the starter or VFD 2 A freestanding starter or VFD furni...

Page 30: ...Diagram on page 32 or on the cover of the control panel for proper connections The purpose of the water flow interlocks is to prevent compressor operation until such time as both the evaporator water...

Page 31: ...wire between 83 81 The alarm is operator programmable The maximum rating of the alarm relay coil is 25 VA 5 Remote on off control of unit can be accomplished by installing a set of dry contacts betwe...

Page 32: ...32 Centrifugal Chillers IM 1044 2 Figure 19 Field Control Wiring Diagram...

Page 33: ...IM 1044 2 Centrifugal Chillers 33 Figure 20 Field Wiring Remote Starter...

Page 34: ...ikin startup technician is responsible is to check the wiring and make the appropriate control changes pLAN Wiring Connect chillers together pLAN RS485 wiring as shown in Figure 21 on the following pa...

Page 35: ...ller Chiller D would be connected to chiller C same as chiller C to chiller B Chiller A PIGTAIL 485 OPDR C A B UCM J10 J11 BLU WHT WHT BLU SHIELD UNIT CONTROL J11 PORT Chiller B 485 OPDR C BLU WHT WHT...

Page 36: ...ence The Modes setpoints will do several different types of operation Normal Efficiency Standby etc as described in the operating manual The same Modes setting must be replicated on each chiller in th...

Page 37: ...starter load leads run to compressor ready for connection when service engineer is on hand for start up Do not connect starter or compressor terminals All interlock wiring complete between control pa...

Page 38: ...contact your Daikin representative Standby Power It is essential that any centrifugal chiller connected to standby power come to a complete stop before being restarted on grid power This is usually n...

Page 39: ...5 volt Circuit Breaker Latch Relay Heater Relay Compressor Relay Oil Pump Overload Relay Reset Button Oil Pump Contactor Oil Pump Starting Capacitor Terminal Board CTB2 Compressor Microprocessor Trans...

Page 40: ...d Figure 28 for solenoid action Note that both solenoids cannot be energized simultaneously Vane Speed Metering Valves The speed at which the capacity control vanes are opened or closed can be adjuste...

Page 41: ...Sump Section SB De energized Section SA De energized From Oil Pump Discharge Adjustable Needle Valves Integral With Four Way Solenoid Valve HOLDING NOTE 4 way solenoid valve and vane close switches ar...

Page 42: ...n in Table 15 can be used for proper operation of the hydraulic system and bearing lubrication system Each unit is factory charged with the correct amount of the recommended lubricant Under normal ope...

Page 43: ...Gal Can 735030432 Rev 47 735030433 Rev 47 735030435 Rev 47 Compressor Oil Label 070200106 Rev OB NOTES 1 Approved oil from two suppliers can be mixed although they have slightly different viscosity 2...

Page 44: ...r from short cycling under light load conditions It also reduces surge potential on heat recovery units The factory setpoint for bringing on hot gas bypass is 40 of RLA Condenser Water Temperature Whe...

Page 45: ...equipment Only authorized and trained service personnel should attempt this service For qualified assistance contact your local Daikin service location After the system is once placed into operation...

Page 46: ...ome foaming can occur but the check valve should limit leakage from other compressor cavities Remove the filter replace with new element and replace filter cover using a new gasket Reopen the valve in...

Page 47: ...IM 1044 2 Centrifugal Chillers 47 Figure 8 Typical Refrigerant Flow Diagram 1 Connections are not necessarily in correct relative location 2 Filter is for burnout protection of the refrigerant...

Page 48: ...dicates a possible insulation defect or moisture and must be further checked CAUTION Never Megger a motor while in a vacuum Severe motor damage can result 6 The centrifugal compressor must rotate in t...

Page 49: ...n result in corrosion erosion sliming scaling or algae formation It is recommended that the service of a reliable water treatment company be used Daikin assumes no responsibility for the results of un...

Page 50: ...reached disconnect the gas cylinder Pressure Testing No pressure testing is necessary unless some damage was incurred during shipment Damage can be determined upon a visual inspection of the exterior...

Page 51: ...uld be interrupted and prestart checks made before attempting to complete refrigerant charge The compressor must not be started at this time Preliminary check must first be completed NOTE It is of utm...

Page 52: ...in some mineral oils Lead The source of lead in Daikin centrifugal chillers is the thread sealant compounds used during chiller assembly The presence of lead in the lubricating oil in Daikin chillers...

Page 53: ...rom previous sample results or after a failure The presence of residual materials from a failure should be taken into consideration in subsequent analysis While the unit is in operation the sample sho...

Page 54: ...ystem Clean Oil Cooler Strainer water X Oil Cooler Solenoid Operation O Oil Appearance clear color quantity O Oil Filter Pressure Drop O Oil Analysis Note 5 X Oil change if indicated by oil analysis X...

Page 55: ...ndling electrical components only fully qualified technicians must attempt service 2 Approach temperature the difference between the leaving water temperature and the saturated refrigerant temperature...

Page 56: ...talled keep it pumped down as shipped from the factory and close all refrigerant valves 5 Keep oil sump valves closed to avoid refrigerant migration to the oil sump Over a long term the refrigerant wi...

Page 57: ...concerning the many services available contact your local Daikin service office Operator Schools Training courses for Centrifugal Maintenance and Operation are held through the year at the Daikin Tra...

Page 58: ...ick on training or call 540 248 9646 to speak to the Training Department Warranty All Daikin equipment is sold pursuant to Daikin standard terms and conditions of sale including Limited Product Warran...

Reviews: