Receiving and Handling
The unit should be inspected immediately after receipt for possible damage.
All
Daikin
centrifugal water chillers are shipped FOB factory and all claims for handling and shipping damage
are the responsibility of the consignee.
Insulation corners from the evaporator's rigging hole locations are shipped loose and should be glued in place
after the unit is finally placed. Neoprene vibration pads are also shipped loose. Check that these items have been
delivered with the unit.
If so equipped, leave the shipping skid in place until the unit is in its final position. This will aid in handling the
equipment.
Extreme care must be used when rigging the equipment to prevent damage to the control panels or refrigerant
piping. See the certified dimension drawings included in the job submittal for the center of gravity of the
unit. Consult the local
Daikin
sales office for assistance if the drawings are not available.
The unit can be lifted by fastening rigging hooks to the outermost four rigging eyes (see Figure 1). Spreader bars
must be used between the rigging lines to prevent damage to the control panels, piping and motor terminal boxes.
Figure 1, WSC Major Component Locations
Unit
Control
Panel
Rigging
Locations
(6) Available
Evaporator
Condenser
Rigging
Locations
(6) Available
Compressor
Starter/VFD,
Mounting Optional
Compressor and
Lubrication Control
Panel, At Rear