6 Requirements
The appliance has to be mounted in the according module carrier, which
is to be operated in a
19'' standard rack with active ventilation
. The re-
quired rails are included in the scope of delivery.
Rack Installation
➡
Ensure a free space of at least 60 cm at the front of the rack in order
to be able to fully open the door.
➡
Ensure a free space of at least 75 cm at the rear of the rack in order to
enable sufficient air circulation and access for maintenance.
➡
Install the rack at a place with limited access (device or server room).
➡
Ensure that the rack is installed in a stable way and is suitable to with
-
stand the weight of the mounted devices.
Device Installation
➡
Install heavy devices at the bottom of the rack.
➡
Note that the temperature in the top of the rack can be higher than
at the bottom.
➡
Plan a distance between the devices in order to allow a better air
circulation.
➡
Ensure a sufficient air circulation by a free space of 10 cm at the front
and rear side of the device.
Operation in the Rack
➡
Keep the doors of the rack closed in order to ensure a sufficient air
circulation.
Secure Earthing
➡
Ensure anytime a proper grounding, preferably through a direct
grounding of the rack.