Application guidelines
88
FRCC.PC.023.A7.22
Manifold compressors
VZH088
Compressor mounting
Oil equalization connection
The tandem is fixed on the frame using the
flexible grommets supplied with the compressor.
The compressors are fixed on the rails (not
included) using rubber grommets, mounting
sleeves, washers (delivered with the
compressors).
Because VZH088 is 0.28 inch smaller than
SH120 and in order to have the oil equalisation
connection at the same level for both
compressors, an additional 0.28 inch rigid spacer
must be added under the VZH088 feet only for
composition of SH120 (see below
drawing).
The level of oil is naturally balanced by a 1”1/8 oil
equalization line.
The kit 120Zxxxx includes a 1”3/4 to 1”1/8
adaptor sleeve (4) & a teflon seal (5) to connect
the oil line to the compressor 1”3/4 oil connector
(8).
The oil line is brazed to the sleeve which is
inserted (depth D=1.97 in) into the compressor
and fitted using rotolock system.
The organ pipe needs to be installed in
the direction indicated by the label attached,
which will ensure best oil balance.
D= 1.97 inch
TOP
1.97 inch
TOP
1.97 inch
13
0.59 inch
HM 8 bolt
Lock washer
Flat washer
Steel mounting
sleeve
Rubber grommet
Nut
Base plate, rails, etc. with enough rigidity
Rigid spacer 13
Fitting for VZH088 in tandem SH120