3. INSTALLATION
8
After placing all modules in the right order on the floor, the modules have to be assembled.
Follow the following points to mount the modules:
•
Adjust the height of the modules with the help of the adjustable feet, so that all
modules are in level and in same height.
•
Use straps (1) to move the modules the last few millimetres. Straps should only be
mounted at the bottom or/and top of the modules.
•
Connect the single modules with the assembly rails (2) which are pushed from the top
over the outside of the frame profile all the way around the unit. The assembly rail can
at difficult accessible space be divided in smaller pieces, which are then inserted over
the frame profiles.
•
To finish the installation all modules have to be connected with the green/yellow earth
connection (3) at the top of the modules.