STEP 2

• Locate 2 more bars2 couplers, and 4 more large joiners.
• Attach 2 large joiners to each of the 2 bars, but this time slide the bars through the long channel on the
underside of the large joiners.
• Connect all 3 bars from this step, using the couplers as shown in Figure 2.2.
• Attach 2 stacking bridges to the large joiners on the left side and 2 on the right.  Leave the large joiner in the
middle empty for now.

STEP 1

• Start building the set by locating and
attaching one stacking bridge to one
baseplate.
• Next, attach one end of a loop to
the

 built-in track joiner on the stacking

bridge

, as shown to the right. Attach the other

end of the loop to the built-in track joiner in
front of the stacking bridge on the baseplate.

•  Attach another loop

 by placing one end in

the unused half of the built-in track joiner on
the baseplate, as shown to the right.  Attach
the other half to the built-in track joiner to the
left of the stacking bridge, at a 90° angle.
•  Next, attach a flexi-curve

 to the built-in

track joiners on either side of the baseplate,
as shown.
•  To complete the step, add a 14" Straight
track
 to the unused half of the stacking
bridge.
• Put this configuration to the side for now.

Built in
Track Joiner

FIGURE 1

First
Loop

Flexi-Curve

Stacking
Bridge

Straight Track

Large Baseplate

Attached on
Built-in Track
Joiner

Built-in
Track Joiner

Second
Loop

FIGURE 2.1

PAGE 3

• Attach 1 large joiner to 1 bar by sliding the bar
through the short channel on the underside of the
large joiner. See Figure 2.1.

The bar goes through the
SHORT CHANNEL on the
uderside of this Large Joiner

FIGURE 2.2

Underside View

long channel

Bar

Couplers

The bar goes through the
LONG CHANNELS of these 2
Large Joiners
.

Stacking
Bridges

Bar

Bar

Stacking
Bridges

The bar goes through the
LONG CHANNELS of these
2 Large Joiners.

Underside View

short
channel

Summary of Contents for Speed Racer ALPINE CHALLENGE

Page 1: ... you haven t missed anything IF A PART IS MISSING OR DAMAGED Speed Racer ALPINE CHALLENGE DARDA CARS 2 CHECK LIST LOOP HALVES 16 7 STRAIGHT TRACK 2 14 STRAIGHT TRACK 6 LARGE BASE PLATE 2 LOOP JOINERS 16 TRACK JOINERS 10 START WIN BOX 1 BARS 18 STACKING BRIDGE 10 LARGE JOINER 10 FLEXI CURVE 8 COUPLER 6 SMALL JOINER 4 TUNNEL 1 MOUNTAIN CUT OUT 2 ICICLES 2 SHEET OF STICKERS 1 Raised edges face down S...

Page 2: ...s shown Using Built In Track Joiners on Baseplates and Large Joiners Building the Mountains Fold one mountain along the score lines Insert one bar into a coupler as shown Place the left side of the mountain into the groove of the bar and slide the left center tab under the coupler Bend the mountain and position the right center tab into the adjoining hole in the coupler Slide the groove of another...

Page 3: ...n the baseplate as shown to the right Attach the other half to the built in track joiner to the left of the stacking bridge at a 90 angle Next attach a flexi curve to the built in track joiners on either side of the baseplate as shown To complete the step add a 14 Straight track to the unused half of the stacking bridge Put this configuration to the side for now Built in Track Joiner FIGURE 1 Firs...

Page 4: ...e other end of the 14 straight track Be sure that the start win box is positioned as shown in Figure 5 Next attach one 7 straight track and one flexi curve using 2 track joiners as shown in Figure 5 Attach one end of another 14 straight track to the flexi curve using a track joiner Then connect the other end of the 14 straight track to the flexi curve on the middle large joiner Second 14 Straight ...

Page 5: ...e tunnel flat on the ground so that it does not impede the cars on the track 3 Mountains can be placed wherever you like so long as they do not impede the cars on the track Attach the second half of the set to the start win box using 2 track joiners Your completed set should now look like Figure 7 Note You will have 2 Track Joiners left over FIGURE 6 2 Assemble the second half of the set which is ...

Page 6: ...e Press the Green button to start both cars simultaneously The winning car will spin the checkered flag to its side of track Flexi Curves Loops 3 14 Straight Track Loop Loops 2 14 Straight Track Loop 14 Straight Tracks 7 Straight Track 7 Straight Track Base Plate with Stacking Bridge Base Plate with Stacking Bridge Start Win Box Items not used in Alt 2 4 Small Joiners 2 14 Straight Tracks 8 Stacki...

Reviews: