2 Transport and storage 

 

2.1 Delivery 

 
If no other agreements have been made, the unit is packed safely and will be delivered 
ex work. Transport damages have to be immediately documented by the carrier or 
another supplier. Please also note the possible damages on the way bill.  
 

2.2 Transport

 

 
The Transport is to be proceeded with care to avoid damages by improper handling or 
carelessness.  
It is important to avoid exposure to violent shocks, otherwise the function and safety of 
the unit cannot be guaranteed. In winter and at risk of frost, the whole unit (Pump, filter 
housing and tank) needs to be emptied before transport.  

Attention:

 Transport of unit (also relocation) only when empty. 

 

2.3 Storage 

 
In order to avoid damages, the installation has to be kept in a dry area with no access for 
unauthorized persons. 
 

Because of risk of frost in winter it is important to observe the following: 

  Empty water hoses, filter housing, tank and pumps 

  Place Water Management in a frost-protected area 

 

Advice for the draining of the tank

Beware: The water temperature of the tank may be up to 80°C. To avoid scalding, we 
strongly recommend to allow the boiler to cool before emtying. To drain remove cap 
“empty tank“ and tilt valve.  
 

 

Cap 
Empty tank „OUT“ 

Valve 

Summary of Contents for C 30 L

Page 1: ...Instruction manual Water Management System C 30 L Manufacturer deconta GmbH Im Geer 20 D 46419 Isselburg Description Water Management C 30 L Type No 545 Serial No ...

Page 2: ...ransport and storage 4 2 1 Delivery 4 2 2 Transport 4 2 3 Storage 4 3 Volume of delivery 5 4 Technical description 5 4 1 Intended use 5 4 2 Unit description 5 5 Technical data 6 6 Initial operation 7 7 Maintenance and care 9 7 1 Daily maintenance 9 7 2 Filter change 9 8 Circuit diagram 11 9 Declaration of conformity 12 ...

Page 3: ...event of non observance deconta assumes no liability To ensure safety during operation of the unit the following must be strictly observed Do not use in potentially explosive areas Necessary repairs and maintenance may only be performed by authorized staff For all repair and maintenance work the device is to be completely disconnected from power supply The safety and protective equipment is to be ...

Page 4: ...unit cannot be guaranteed In winter and at risk of frost the whole unit Pump filter housing and tank needs to be emptied before transport Attention Transport of unit also relocation only when empty 2 3 Storage In order to avoid damages the installation has to be kept in a dry area with no access for unauthorized persons Because of risk of frost in winter it is important to observe the following Em...

Page 5: ...ical description 4 1 Intended use During asbestos sanitation works within closed rooms you have to exclude that the asbestos fibres leave the sanitation area uncontrolled and endanger the human health and the environment For this reason personnel must leave the sanitation area through a lock system and take a shower while leaving The deconta water treatment system heats up the shower water and tak...

Page 6: ...hnical data Volume service water 60 Liter Tank filling automatic Heating capacity 2000 W Filter stages 3 Filter size 10 Power supply 230 V Power consumption 10 A Water connections System Geka Dimensions L x W x H 576 x 606 x 1085 mm Weight 53 kg technical changes reserved ...

Page 7: ...ll come loose after running Unplug Establish hose connections o Connection Water inlet with pipeline network o Connection Warm water shower water with shower top o Connection Sewage IN with shower tray o Connection Sewage OUT with sewage system Fill waste water pump with water Connect to power Set Temperature selector at the bottom of tank to level 3 heating phase begins duration approx 80 minutes...

Page 8: ...ety instructions During works on the device always disconnect the plug Operate the device only with mains which are secured with fault current protection switch Never operate the device without water In case of frost risk empty the device by opening the stopcock Do not change the adjustment of the temperature in the pre mixing unit CAUTION Danger of scalding Check outlet temperature before every s...

Page 9: ...dirt Control of fine filter via manometer 7 2 Filter change The Manometer controls the fine filter We recommend a filter change at approx 3bar Attention Change Filter only when device is switched off Demount dirty filters only in wet shape to avoid contamination Use approved filters only Do not use damaged filter candles Filter head screw Manometer filter control Cap nut ...

Page 10: ... new filter candles Pay attention to correct fit and cleanliness of the seal ring Tighten the nut The suction hoses pumps filter housings and filter are contaminated after the first use Repairs and maintenance have to be executed only under the observance of all relevant safety measures All the filters mentioned have to be disposed of according to the legal terms ...

Page 11: ...Instruction manual Water Management Boiler system C 30 L Seite 11 8 Circuit diagram ...

Page 12: ...mbH Im Geer 20 D 46419 Isselburg Product Water Management C 30 L Type 545 The design of the unit complies with EU Machine directive 2006 42 EG the following directives EU Low voltage directive 2006 95 EG Applied harmonised standards EN 292 EN 60335 1 Applied national standards DIN VDE 0701 DIN VDE 0702 W Weßling Isselburg 24 06 2015 ...

Reviews: