9
MCA
Pro
45/65/90/115
MCA-Pro ISM Rv.4.1 2/2017
Safety Information and Codes
a.
In the event that the side wall horizontally vented gas fueled equipment is installed in a crawl
space or an attic, the hard
wired carbon monoxide detector with alarm and battery back-up may be
installed on the next adjacent floor level.
b.
In the event that the requirements of this subdivision cannot be met at the time of completion of
installation, the owner
shall have a period of thirty (30) days to comply with the above
requirements; provided, however, that during said thirty (30)
day period, a battery operated carbon
monoxide detector with an alarm shall be installed.
2.
APPROVED CARBON MONOXIDE DETECTORS:
Each carbon monoxide detector as required in
accordance with the above
provisions shall comply with NFPA 720 and be ANSI/UL 2034 listed and
IAS certified.
3.
SIGNAGE:
A metal or plastic identification plate shall be permanently mounted to the exterior of
the building at a minimum
height of eight (8) feet above grade directly in line with the exhaust vent
terminal for the horizontally vented gas fueled heating
appliance or equipment. The sign shall read,
in print size no less than one-half (1/2) inch in size,
"GAS VENT DIRECTLY BELOW.
KEEP CLEAR OF
ALL OBSTRUCTIONS". (Continued)
1.
The equipment listed in Section 10 entitled "Equipment Not Required To Be Vented" in the
most current edition of NFPA
54 as adopted by the Board; and
2.
Product Approved side wall horizontally vented gas fueled equipment installed in a room or
structure separate from the
dwelling, building or structure used in whole or in part for residential
purposes.
(c) MANUFACTURER REQUIREMENTS - GAS EQUIPMENT VENTING SYSTEM PROVIDED. When the
manufacturer of Product
Approved side wall horizontally vented gas equipment provides a
venting system design or venting system components
with the equipment, the instructions
provided by the manufacturer for installation of the equipment and the venting
system shall
include:
1.
Detailed instructions for the installation of the venting system design or the venting system
components; and
2.
A complete parts list for the venting system design or venting system.
(d) MANUFACTURER REQUIREMENTS - GAS EQUIPMENT VENTING SYSTEM NOT PROVIDED. When
the manufacturer of a
Product Approved side wall horizontally vented gas fueled equipment does
not provide the parts for venting the flue gases,
but identifies "special venting systems", the
following requirements shall be satisfied by the manufacturer:
1.
The referenced "special venting system" instructions shall be included with the appliance or
equipment installation
instructions; and
2.
The "special venting systems" shall be Product Approved by the Board, and the instructions for
that system shall include a
parts list and detailed installation instructions.
(
e) A copy of all installation instructions for all Product Approved side wall horizontally vented gas
fueled equipment, all
venting instructions, all parts lists for venting instructions, and/or all
venting design instructions shall remain with the
appliance or equipment at the completion of the
installation.
……………….[End of Extracted Information From 248 CMR 5.08 (2)]…………………
4. INSPECTION:
The state or local gas inspector of the side wall horizontally vented gas fueled
equipment shall not
approve the installation unless, upon inspection, the inspector observes
carbon monoxide detectors and signage installed
in accordance with the provisions of 248 CMR
5.08(2)(a)1 through 4.
(b) EXEMPTIONS: The following equipment is exempt from 248 CMR 5.08(2)(a)1 through 4: