Table 11.9
Shore connection breaker trip flowchart
Yes
Shore
connection
breaker trip
Open SCB
SCB opened
No
Yes
SCB tripped
Alarm
1.
Open SCB:
When a trip is required, the controller activates the
Breakers > Shore
connection breaker > Control > SCB open
output to open the breaker.
2.
SCB opened:
The controller checks whether the breaker has opened:
•
If the breaker has opened, the trip is successful.
•
If the breaker has not opened, the controller activates the
SCB opening failure
alarm.
11.4 Other SHORE connection controller functions
11.4.1 Ship-to-ship
A SHORE connection controller can be used to supply power to another ship using the ship-to-ship function. This may be useful
where quay space is limited.
The ship-to-ship function can be active in several SHORE connection controllers in the section at the same time. These ship-to-ship
functions operate independently.
Input
Assign the input under
Configure > Input/output
. Select the hardware module, then select the input to configure.
Table 11.10
Hardware required in addition to the minimum standard controller wiring
Function
I/O
Type
Details
Power management >
Ship-to-ship supply
Digital input Continuous
When the input is activated, the shore connection can supply another ship
with power. The controller also activates the
Ship-to-ship active
inhibit. Note:
Once the SCB closes, the ship-to-ship function remains activated until the
breaker opens (even if this input is deactivated).
Parameters
Configure these parameters under
Configure > Parameters > Local power management > Shore connection ship-to-ship >
Open point
.
Parameter
Range
Default
Comment
Open point
enabled
Not enabled, Enabled
Not enabled
Not enabled
: The power management system can open the shore
connection breaker (SCB) at any load.
Enabled
: For the power management system to open the SCB, the
load on the SCB must be less than the value in
Open when power
below
.
Open when power
below
2 to 100 % of the shore
connection nominal
power
5 %
For the power management system to open the SCB, the receiving
ship has to decrease the load until it is below this value.