STEP 1 

Hot Water

STEP 2 

Ozone Enriched 

Cold Water

1. Total reduction of Aceto-

bacter (which contributes 
to Volatile Activity)

2. Total Reduction of Brettan-

omyces (or all wild yeasts)

3. Overall barrel freshning

None

1.0-3.0 MInutes

4. Light

1.0 Minute 1.5 MInute

5. Heavy

2.0 MIn-
utes

2.0 Minutes

3D-3. Direct Food Contact - Spray Nozzles
Applications vary. Please contact DEL Ozone for 
advice/consultation at 800-676-1335.

3D-4. Testing Dissolved Ozone Level (HACH) in 
System Effluent Water Flow
Materials Required

1.  HACH Indigo Blue AccuVac high range dis-

solved ozone test kit (DEL P/N 6-0116)

2.  5 gallon plastic pail (pre-cleaned)
3.  Cold potable supply water for MPI-300

Procedure

1.  Familiarize self with HACH AccuVac test kit.

2.  Start-up MPI-300, place and hold spray wand in 

5 gallon pail, and allow to flow for three to four 

minutes (NOTE: ensure the tip of the spray  

 

wand is approximately two inches above the    

bottom of the pail).

3.  Thoroughly rinse hands, ampule, and plunger 

under the pail’s overflow for one minute.

4.  Immediately take a water sample using the 

ampule (following the HACH instructions) from 

the middle of the pail at least one inch below    

the water surface.

5.  Gently shake the ampule.
6.  Immediately compare the color of the ampule to 
7.  the supplied color wheel with thumb covering 

the numerical readings. Once a color match is 
determined, move thumb and take numerical 
reading.

SECTION 4 MAINTENANCE AND 
SERVICE

4A.   Preventative Maintenance Schedule

DAILY:

1.  Check ozone generator for proper operation.

- Make sure green indicator lights are lit during 

operation.

MONTHLY:

1.  Turn off system, unplug from power.
2.  Remove and clean air filter located under “dry 

section.”

    - Remove plastic cover.
  - 

Rinse filter in warm, soapy water and allow to dry.

    - Replace filter. (DEL P/N 7-1153)

3.  Perform general cleaning of cabinet exterior.
4.  Using clean/dry compressed air, blow out the 

interior of cabinet, taking special care around 
small components and wiring.

5.  Check for debris in the debris screen located in   

the source water inlet fitting. Clean & reinstall.

6.  Check air in the tires and their general 

condition.

ANNUALLY:

1.  Remove and replace compressor air filter 

cartridge using DEL P/N 7-1132.

EVERY 10,000 HOURS:

1.  Rebuild compressor.

    - Purchase compressor rebuild kit. (DEL P/N           

    2-1007 - See Section 5B for ordering infor- 

            mation)
    - Follow instructions in compressor rebuild kit.

EVERY 18,000 HOURS:

1.  Replace ozone generation cell. (DEL P/N 9-0925)

4B. Trouble Shooting

Knowledge of electrical applications is required 
for trouble shooting. Contact a certified electrician 
if you are unsure of your ability to service the 
equipment. If any condition persists, call 800-676-
1335 or for international call 805-541-1601 for 
technical assistance.

Symptom: “OZONE ON” green indicator light out 
when switch is in the “ON” position and “PUMP ON” 
light is on.

1.  Check inside control panel for fault lights.

a.  See Low Vac & Hi Temp fault light sections.

2.  Check internal fuse.

a.  Replace if blown. (3 amp - AGC 3)

3.  Cabinet door ajar.

a.  Close and latch door.

Summary of Contents for MPI-300

Page 1: ...Installation Operations Manual 3580 Sueldo Street San Luis Obispo CA 93401 800 676 1335 o3info delozone com www delozone com 4 0700 Rev E MPI 300 Multi Point Intervention Ozone Sanitation System...

Page 2: ...orth in the owner s manual ANTIMICROBIAL CLAIMS This device has been determined acceptable for use as an ozone generating device providing sanitization and disinfection of hard inanimate pre cleaned s...

Page 3: ...3D Standard Operating Procedures 3 SECTION 4 Maintenance Service 4A PM Schedule 4 4B Trouble Shooting 4 SECTION 5 Replacement Parts 5A Ordering Information 4 5B Standard Replacement Parts List 4 SECTI...

Page 4: ...M min Weights Dimensions 25 5 H x 24 5 W x11 D 100 lbs Ambient Temp 40 F 90 F not to exceed 90 F 1C Layout Accessories The MPI 300 is a low pressure ozone enriched cold water surface sanitizer Interna...

Page 5: ...ed to a location close to your process This can be a level location either indoors or outdoors For all systems allow for access to protected electrical power and required water connections The point o...

Page 6: ...inal sanitizing rinse leaving no residual 3D 1 Surface Sanitation The spray can be directed on all wettable wood metal concrete and plastic surfaces including floors drains walls conveyors containers...

Page 7: ...numerical reading SECTION 4 MAINTENANCE AND SERVICE 4A Preventative Maintenance Schedule DAILY 1 Check ozone generator for proper operation Make sure green indicator lights are lit during operation MO...

Page 8: ...0 1 0 2 770 3740 0 2 6 7 1 1 2 5 Rotavirus 0 006 0 06 3810 6480 0 2 2 1 0 01 0 05 G lamblia cysts 0 5 0 6 47 150 G muris cysts 1 8 2 0 1400 7 2 18 5 30 630 6A 2 Materials Selection Materials Aqueous O...

Page 9: ...one to which workers may be exposed averaged over 8 hours 5 days a week OSHA Gaseous ozone concentrations above 0 02 PPM are detectable by humans Inasmuch sections 6C through 6H of this manual discuss...

Page 10: ...ure times ranging from 5 minutes to 10 hours 6D 2 Ventilation It is mandatory that general and local exhaust ventilation be provided to dilute and disperse small amounts of ozone into the outside atmo...

Page 11: ...34 may be used for personnel or area monitoring for exposure times ranging from 5 minutes to 10 hours For higher resolution the ChromAir ozone badge may be used in conjunction with the ChromAir ozone...

Page 12: ...ng has ceased start artificial respiration rescue breathing is the most effective method until breathing has been restored 2 Send for medical assistance immediately 3 If absent begin cardiopulmonary r...

Page 13: ...10 MPI 300 Installation Operations Manual APPENDIX A DAILY DATA LOG...

Page 14: ...11 MPI 300 Installation Operations Manual APPENDIX A...

Page 15: ...12 MPI 300 Installation Operations Manual APPENDIX B EMERGENCY INFORMATION...

Page 16: ...13 MPI 300 Installation Operations Manual...

Page 17: ...14 MPI 300 Installation Operations Manual APPENDIX C SAFETY...

Page 18: ...pping Classification NON REGULATED I PHYSICAL DATA Boiling Point 212 F Freezing Point 32 F Specific Gravity 1 0 Solubility in Water COMPLETE Evaporation Rate APPROX 1 Physical Form LIQUID Appearance O...

Page 19: ...prevent irritation and drying of the skin V EMERGENCY AND FIRST AID PROCEDURES Eye Contact If exposure to water containing aqueous solution of ozone causes irritation to eyes flush eyes with plenty of...

Page 20: ...e periodic exposure levels established by OSHA for worker safety through the use of DEL s ozone management technology Precautions To Be Taken In Handling Aqueous solutions of ozone in potable water sh...

Page 21: ...E WARRANTED ONLY FOR THE BALANCE OF THE ORIGINAL TWO 2 YEAR WARRANTY PERIOD NOTE USE ONLY DEL OZONE AUTHORIZED REPLACEMENT AND MAINTENANCE PARTS USE OF ANY OTHER PART S WILL AUTOMATICALLY VOID THIS WA...

Page 22: ...3580 Sueldo Street San Luis Obispo CA 93401 800 676 1335 o3info delozone com www delozone com EPA Estab No 071472 CA 001...