Installation guidelines
Deutschmann Automation GmbH & Co. KG
31
UNIGATE
®
fieldbus gateway UNIGATE
®
EL - DeviceNet
™
V. 1.0
22.6.17
11 Installation guidelines
11.1 Installation of the module
The module with the dimensions 23 x 115 x 116 mm (W x D x H)
has been developed for switch
cabinet use (IP 20) and can thus be mounted only on a standard mounting channel (deep
DIN-rail to EN 50022).
11.1.1 Mounting
•
Engage the module from the top in the top-hat rail and swivel it down so that the module
engages in position.
•
Other modules may be rowed up to the left and right of the module.
•
There must be at least 5 cm clearance for heat dissipation above and below the module.
•
The standard mounting channel must be connected to the equipotential bonding strip of the
switch cabinet. The connection wire must feature a cross-section of at least 10 mm².
11.1.2 Removal
•
First disconnect the power supply and signal lines.
•
Then push the module up and swivel it out of the top-hat rail.
Vertical installation
The standard mounting channel may also be mounted vertically so that the module is mounted
turned through 90°.
11.2 Wiring
11.2.1 Connection systems
The following connection systems must resp. may be used when wiring the module:
•
Standard screw-type/plug connection (power RS + DeviceNet)
a) In the case of standard screw-type terminals, one lead can be clamped per connection point. It
is best to then use a screwdriver with a blade width of 3.5 mm to firmly tighten the screw.
Permitted cross-sections of the line:
•
Flexible line with wire-end ferrule:
1 x 0.25 ... 1.5 mm²
•
Solid conductor:
1 x 0.25 ... 1.5 mm²
•
Tightening torque:
0.5 ... 0.8 Nm
b) The plug-in connection terminal strip is a combination of standard screw-type terminal and
plug connector. The plug connection section is coded and can thus not be plugged on the
wrong way round.
11.2.1.1 Power supply
The device must be powered with 10..33 V DC.
•
Connect the supply voltage to the 4-pole plug-in screw terminal in accordance with the labelling
on the device.
11.2.1.2 Equipotential bonding connection
The connection to the potential equalization automatically takes place it is put on the DIN-rail.