8
3. the initial use of new equipment
:
the new equipment of the factory contain a protective effect lubricants,so
the initial use of new equipment need to join the clean water of few soap to
take in to clean ,the flollowing step is cleaning
:
⑴
add to suction tube containing a little soapy water in the buckets
⑵
add to the waste will be returned in the paint barrels\buckets.
(3)return valve will be installed in the vertical direction .
(4)open equipment power switch..
(5)let soapy water to peration equipment in the equipment within the circle ,until the
outflow of clean water from the return tube .
II preparetive before spraying
:
before spraying ,they must first determine spray paint has been good
and have been initially harmonic filtering ,otherwise undesirable coating
equipment will in creas wear and reduce the life span of equipment .in
addition ,each time before spraying ,the paint must be used by delicated
diluent (such as spraying latex paint water can be used )to allow equipment
to cycle again and again spraying ,the following is operation steps
:
⑴
add suction tube will be fitted with special diluent or clean in the bucket.
⑵
add to the waste will be returned in paint bucket.
⑶
Pressure control buttons will be set in the middle (yellow areas) but the bottom
of the location of equipment functioning.
⑷
return valve will be installed in the vertical direction.
⑸
Power equipment opened.
⑹
equipment to operation 15 to 30 seconds until the clean diluent from the outflow
of return
⑺
shut the powers switch.
⑻
set the reflux valve to the position of level.
⑼
turn on the power switch