Lowering the floor-slab formwork
➤
Lower the floor-slab formwork by striking the wedge
on the lowering head with a hammer.
Removing parts that are no longer needed
➤
Turn the secondary beams over onto their sides, pull
them out and put them in the stacking pallet.
Leave the beams under the panel-joints in place.
➤
Take out the ProFrame panels and put them in the
stacking pallet.
➤
Remove the remaining secondary beams and the
primary beams, and put them in the stacking pallet.
Removing the floor props
1)
Hold the inner tube with one hand.
2)
Open the fastening clamp to unfix the inner tube.
Guide this by hand while lowering it into the outer
tube.
➤
Put the removable folding tripods and props in the
stacking pallet.
Reshoring
➤
Before pouring the next floor-slab (i.e. above the one
that has just been stripped), put up reshoring props.
9720-007
9720-008
9720-009
When lifting the equipment to the next storey, it
is better to transport the floor props and the low-
ering heads separately (the floor props on their
own can be stored much more space-savingly
in the stacking pallet).
☞
For further information (number of props etc.),
see "Reshoring props, concrete technology and
striking"
9720-006