User Information
Framed formwork Framax Xlife plus
Wall formwork
93
999811202 - 04/2019
Lifting the platform onto the formwork:
➤
Attach a four-part lifting chain (e.g. Doka 4-part chain
3.20m) to the pouring platform and hoist it towards
the formwork.
➤
Fix the pouring platform to the top of the formwork.
➤
Detach the four-part lifting chain.
The safety hooks latch into place automatically.
The pouring platform is now secured against accidental
lift-out.
Lifting the platform off the formwork:
➤
Attach a four-part lifting chain to the pouring platform
and raise it.
When the pouring platform is raised by the four-part
lifting chain on the safety hook, the platform is auto-
matically unlocked.
Transporting, stacking and storing
a ... 268
cm
b ... 295
cm
c... 10 x 18.7
cm
d... 31
cm
e... approx. 218
cm
f... 142
cm
g... 50
cm
A
Safety hook
Do a sight check to make sure that the safety
hooks have latched into place!
9727-397-01
9727-399-01
A
9727-401-01
Stack of 10 Framax pouring platforms U
Single collapsed
platform
b
a
c
d
e
9727-398-01
9727-393-01
f
g
Summary of Contents for Framed formwork Framax Xlife plus
Page 2: ...2 999811202 04 2019 User Information Framed formwork Framax Xlife plus ...
Page 51: ...User Information Framed formwork Framax Xlife plus Wall formwork 51 999811202 04 2019 ...
Page 70: ...70 999811202 04 2019 Wall formwork User Information Framed formwork Framax Xlife plus ...
Page 117: ...User Information Framed formwork Framax Xlife plus Wall formwork 117 999811202 04 2019 ...
Page 127: ...User Information Framed formwork Framax Xlife plus General remarks 127 999811202 04 2019 ...
Page 139: ...User Information Framed formwork Framax Xlife plus Component overview 139 999811202 04 2019 ...