Start-up phases – Lifting unit attached on one side
Original Operating Instructions
Platform SCP
Start-up phases – Lifting unit attached on one side
Starting up
The modular design of the Platform SCP means that
many different combinations are possible.
Depending on the project, the actual design may thus
differ very greatly from the basic type described here.
➤
In these cases, you should discuss the assembly
procedure with your Doka technician.
➤
Follow the shop drawing / assembly plan.
☞
Important note:
▪
Prepare a sufficiently large assembly area.
▪
A hard, flat, firm surface is needed!
☞
In order to explain the entire lifting sequence as
simply as possible, the repetitive actions
involved are described in detail in separate sec-
tions of this booklet.
The sections in question are:
▪
Preparing the positioning points and suspen-
sion points (see "Anchoring on the struc-
ture").
▪
Closing the formwork (see 'Closing the form-
work').
▪
Striking (see 'Opening the formwork').
For instructions on tying and joining the form-
work elements, and on cleaning them and using
concrete release-agents, see the User Informa-
tion booklets 'Large-area formwork Top50' and
'Framed formwork Framax Xlife'.
WARNING
Falling hazard!
➤
Do not step onto the pouring platforms until
the formwork is closed!
➤
Use personal fall arrest systems to protect
against fall hazards when working on
unsafeguarded drop-off edges (e.g. Doka
personal fall-arrest set).
Summary of Contents for Platform SCP
Page 2: ...2 999805802 03 2016 Original Operating Instructions Platform SCP ...
Page 3: ...Original Operating Instructions Platform SCP 3 999805802 03 2016 ...
Page 31: ...Original Operating Instructions Platform SCP Anchoring on the structure 31 999805802 03 2016 ...
Page 61: ...Original Operating Instructions Platform SCP Start up phases 61 999805802 03 2016 ...
Page 114: ...114 999805802 03 2016 Design variants Original Operating Instructions Platform SCP ...