Original Operating Instructions
Platform SCP
Start-up phases – Lifting unit attached on one side
139
999805802 - 03/2016
1st casting section
➤
Apply concrete release agent and set up one side of
the formwork.
➤
Place the reinforcement.
➤
Mount the positioning-points.
➤
Set up the opposing formwork and place the ties.
➤
Pour the 1st section.
a ... height of casting section: 2700
mm - 4250
mm
b ... min. 500 mm
c ... min. 350
mm
➤
Open the formwork.
➤
Clean the formwork.
➤
Set the gang-form down on a flat surface, with the
form-ply facing downwards.
➤
Prepare the formwork for the climbing operation.
98058-461-03
b
c
a
Summary of Contents for Platform SCP
Page 2: ...2 999805802 03 2016 Original Operating Instructions Platform SCP ...
Page 3: ...Original Operating Instructions Platform SCP 3 999805802 03 2016 ...
Page 31: ...Original Operating Instructions Platform SCP Anchoring on the structure 31 999805802 03 2016 ...
Page 61: ...Original Operating Instructions Platform SCP Start up phases 61 999805802 03 2016 ...
Page 114: ...114 999805802 03 2016 Design variants Original Operating Instructions Platform SCP ...