Schematic sequence of start-up phases
Pour the 1st section.
1st casting
section
Position the main working platform.
Erect the vertical scaffold.
2nd casting
section
Erect the girder grille.
Erect the enclosure and working platform.
Raise the platform to the next casting section.
Pour the 2nd section.
Erect the suspended platforms in the shaft cores
where there is a base beam.
Raise the platform to the next casting section.
Pour the 3rd section.
3rd casting
section
98058-432-02
98058-422-15
98058-470-01
98058-416-28
Summary of Contents for Platform SCP
Page 2: ...2 999805802 03 2016 Original Operating Instructions Platform SCP ...
Page 3: ...Original Operating Instructions Platform SCP 3 999805802 03 2016 ...
Page 31: ...Original Operating Instructions Platform SCP Anchoring on the structure 31 999805802 03 2016 ...
Page 61: ...Original Operating Instructions Platform SCP Start up phases 61 999805802 03 2016 ...
Page 114: ...114 999805802 03 2016 Design variants Original Operating Instructions Platform SCP ...