46
999805802 - 03/2016
Start-up phases
Original Operating Instructions
Platform SCP
Attaching the girder grille
Attaching the pre-assembled girder
grille
➤
Mount temporary platforms (site-provided).
➤
Attach crane suspension tackle to the girder grille.
➤
Crane-lift the girder grille to the vertical profiles.
➤
Release the clamping connections in the area of the
Vertical profiles 150.
➤
Push Clamping plates WU30 on to the Vertical pro-
files 150.
➤
Carefully lower the grille-beam unit on to the Vertical
profiles 150.
☞
▪
Comply with the tolerances specified in the
shop drawing / assembly plan.
▪
Take actual measurements and verify them.
The vertical scaffolds must correspond to the
support points on the girder grille.
▪
If any part of the girder grille does not have
enough support points during assembly, suf-
ficiently strong supports must be provided at
site.
The loads imposed on individual supports
are shown in the project plans.
A
Temporary platform
B
Pre-assembled girder grille
98058-422-10
A
A
A
B
Ensure that the Clamping plate WU30 is in the
correct position.
Summary of Contents for Platform SCP
Page 2: ...2 999805802 03 2016 Original Operating Instructions Platform SCP ...
Page 3: ...Original Operating Instructions Platform SCP 3 999805802 03 2016 ...
Page 31: ...Original Operating Instructions Platform SCP Anchoring on the structure 31 999805802 03 2016 ...
Page 61: ...Original Operating Instructions Platform SCP Start up phases 61 999805802 03 2016 ...
Page 114: ...114 999805802 03 2016 Design variants Original Operating Instructions Platform SCP ...