Original Operating Instructions
Platform SCP
Start-up phases
65
999805802 - 03/2016
➤
Mount Platform roller units on the platform decking.
a ... 50
mm
Threaded-fastener material required
▪
2 square bolts M10x60
▪
2 washers A10.5
▪
2 hexagon nuts M10 (self-locking)
➤
Final mounting of ladders, manholes and other
safety devices (see the section headed 'Ladder sys-
tem').
➤
Close off all openings in the decking on the main
working platform and on the suspended platform.
➤
Pin distribution bolts to the Vertical profiles FRQ
120
as lifting stops and secure with spring cotters.
a ... casting section 150
mm
➤
Apply concrete release agent and set up one side of
the formwork.
➤
Adjust the formwork.
➤
Mount the 'Boxes for latch'.
➤
Place the reinforcement.
➤
Close the formwork and tie it.
J
Platform roller unit
e
98058-445-05
J
98058-406-13
a
Summary of Contents for Platform SCP
Page 2: ...2 999805802 03 2016 Original Operating Instructions Platform SCP ...
Page 3: ...Original Operating Instructions Platform SCP 3 999805802 03 2016 ...
Page 31: ...Original Operating Instructions Platform SCP Anchoring on the structure 31 999805802 03 2016 ...
Page 61: ...Original Operating Instructions Platform SCP Start up phases 61 999805802 03 2016 ...
Page 114: ...114 999805802 03 2016 Design variants Original Operating Instructions Platform SCP ...