94
999805802 - 03/2016
Pre-assembly
Original Operating Instructions
Platform SCP
Assembling the enclosure
Enclosure element
a ... max. 2.00
m
b ... max. 4.00
m
c ... max. 2.00
m
Assembly
➤
Place Doka beams H20 on hardwood blocking.
➤
Screw plank offcuts to the ends of the Doka beams
H20 to take the fasteners for the end planks.
➤
Screw planks 5x20 cm to the plank offcuts with uni-
versal countersunk screws 6x90.
➤
Fix Enclosure clamps SCP onto the webs of the H20
beams, using hexagon bolts.
Width-across 30
mm
Hole diameter: 22
mm
Included in scope of supply:
▪
2 hexagon bolts M20x90
▪
2 washers 20 (EN ISO 7089)
▪
2 hexagon nuts M20, strength grade 8
(EN ISO 4032 / DIN 934)
A
Doka beam H20
B
Plank, 5x20 cm
C
Enclosure clamp SCP
☞
Important note:
If 'a' >2.0
m or 'b' >4.0
m, then an extra stiffen-
ing reinforcement must be added in the middle
of each of these spans.
a
a
b
c
98058-452-02
A
A
C
C
B
B
98058-452-08
A
Doka beam H20
B
Plank, 5x20 cm
A
Doka beam H20
C
Enclosure clamp SCP
98058-452-05
A
B
98058-452-04
A
C
Summary of Contents for Platform SCP
Page 2: ...2 999805802 03 2016 Original Operating Instructions Platform SCP ...
Page 3: ...Original Operating Instructions Platform SCP 3 999805802 03 2016 ...
Page 31: ...Original Operating Instructions Platform SCP Anchoring on the structure 31 999805802 03 2016 ...
Page 61: ...Original Operating Instructions Platform SCP Start up phases 61 999805802 03 2016 ...
Page 114: ...114 999805802 03 2016 Design variants Original Operating Instructions Platform SCP ...