56
999805802 - 03/2016
Start-up phases
Original Operating Instructions
Platform SCP
Finishing the platform and enclosure
Mounting the platforms on the girder
grille
➤
Attach the crane suspension tackle to the working
platform.
➤
Crane-lift the pre-assembled working platform and
guide it towards the girder grille with the aid of tag-
lines.
➤
Bolt Doka beams H20 on to the girder-grille profile
U300 with Beam clamps U300 double.
➤
Fix the Beam clamps U300 double in the Doka
beams H20 with universal countersunk screws
5x50.
➤
Detach the crane suspension tackle from the work-
ing platform.
98058-416-10
A
Grille beam U300
B
Doka beam H20
C
Beam clamp U300 double
D
Universal countersunk screws 5x50
98058-417-01
B
A
D
C
Summary of Contents for Platform SCP
Page 2: ...2 999805802 03 2016 Original Operating Instructions Platform SCP ...
Page 3: ...Original Operating Instructions Platform SCP 3 999805802 03 2016 ...
Page 31: ...Original Operating Instructions Platform SCP Anchoring on the structure 31 999805802 03 2016 ...
Page 61: ...Original Operating Instructions Platform SCP Start up phases 61 999805802 03 2016 ...
Page 114: ...114 999805802 03 2016 Design variants Original Operating Instructions Platform SCP ...