Step 6
A temporary intermediate level can be installed at the
height of the guardrail ledgers for the installation of the
advanced guardrail on the next level up.
➤
For this purpose, two ledgers are installed at a height
of 1.0m above the base of the scaffold and decks are
inserted.
The longitudinal ledgers already installed on the upper
deck level now function as the handrails.
➤
From the temporary working level, the guardrail ledg-
ers as well as the decks of the next scaffolding level
are installed, and the decks are secured with the
wind latch.
As an alternative to the temporary decking level, a sin-
gle-hanging step ladder can also be used from which
the advancing guardrail and the decking in the next
scaffolding level can be installed.
Step 7
When no additional level is required:
➤
When no additional level is required: If no additional
level is required, 1.0m long vertical posts can be
added as guardrail posts on the inner side and at the
end of the scaffold top level. The decking level can
now be accessed with the installed guardrails. In
order to have working access, toe boards are
required to be installed.
The steel planks used for the assembly at the base
level are no longer needed unless the planks are used
for access.
Step 8
When no additional level is required:
➤
If additional level(s) is required, follow steps 4
through 7 of the assembly guide.
➤
Install 2.0m long vertical posts on the top level for
inner and outer sides. The inner side protection may
be omitted if the gap between the scaffold and the
facade is less than 30cm.
The steel planks used for the assembly at the base
level are no longer needed unless the planks are used
for access.