User Information
Load-bearing tower Staxo 100
Horizontal assembly
33
999804302 - 02/2018
➤
Close the anti-liftout guard.
Mount the toeboard
To create a safe workplace, toeboards must be
mounted:
➤
Hook the Staxo
100 toeboards onto the safety-catch
bolts.
➤
Fit the site-provided planks.
➤
Fix the planks with nails.
Optionally: Railings on the top 'storey'
To meet very stringent safety requirements, 'mounted-
ahead' railings can be fitted in the top section.
This is done in line with the instructions given in
'Assembling towers in the upright with 'mounted-ahead'
railings'.
➤
Mount the Staxo side railings and secure them with
a Spring locked connecting pin 16mm to prevent
accidental lift-out.
Close-up 1
➤
Mount Staxo front railings and secure them with a
Spring cotter
5mm to prevent accidental lift-out.
Close-ups 2 and 3
Having scaffold planking units in the top ‘sto-
rey’ makes it easier to carry out assembly work
on the towerframe superstructure.
Determining the right plank-length: Centre-to-
centre distance between the frames, minus
10
cm
A
Staxo 100 toeboard
B
Safety-catch bolt
C
Plank
Tr842-200-03
Tr772-203-01
C
A
B
B
L
Staxo side railing
M
Staxo front railing
N
Spring locked connecting pin 16mm
O
Spring cotter 5mm
2
3
L
M
L
M
1
98003-312-01
N
98003-312-02
98003-312-03
98003-312-04
O