User Information
Load-bearing tower Staxo 100
Assembling towers in the upright
35
999804302 - 02/2018
Assembling towers in the upright
Assembling towers in the upright with 'mounted-ahead' railings
As a rule:
▪
Arrow on the frame must point up.
(= yellow locking spring down)
▪
Slide the diagonal cross onto the safety-catch bolt
and immediately secure it with the safety catch.
Example with Heavy-duty screw jack 70 and 4-way
screw-jack head.
NOTICE
▪
Erect the load-bearing tower in the vertical
on ground that is statically capable of sup-
porting the load.
▪
If the load-bearing tower is over 6
m high,
back-stay it or combine it with other towers.
98003-206-01
98003-233-01
NOTICE
When erecting the tower, make sure that the
climbing rungs are in the correct position rela-
tive to the scaffold planking units.
98003
-2
56
-01