Assembling towers in the upright
User Information
Load-bearing tower Staxo 100
Assembling towers in the upright with 'mounted-ahead' 1.20m frames
General remarks:
▪
Arrow on frame must be pointing upwards.
(= yellow locking spring at bottom)
▪
Slide the diagonal cross onto the safety-catch bolt
and immediately secure it with the safety catch.
e.g. with Heavy duty screw jack 70 and 4-way screw-
jack head.
Erecting the first storey
➤
Place a Split nut B on the Heavy-duty screw jack 70,
push the two halves together and secure it with the
spring locking pin.
➤
Press the yellow locking springs on the frame
inwards (to open) – the connection sleeves can now
be moved freely.
➤
Insert the Heavy duty screw jacks 70 into the frames.
➤
Link the frames with diagonal crosses.
NOTICE
▪
Erect the load-bearing tower in the vertical
on ground that is statically capable of sup-
porting the load.
▪
If the load-bearing tower is over 6
m high,
back-stay it or combine it with other towers.
98003-205-01
98003-233-01
Make sure that the spring locking pin points
downwards when it is secured.
A
Split nut B
B
Heavy duty screw jack 70
C
Spring locking pin
D
Frame
E
Yellow locking spring
F
Diagonal cross