Load-bearing tower Staxo 100
Assembling towers in the upright
45
999804302 - 02/2018
Erecting further storeys
➤
Add further frames in the same way as for the 3rd
'storey', and brace them in the vertical with diagonal
crosses.
Mount the toeboard
To create a safe workplace, toeboards must be
mounted:
➤
Hook the Staxo
100 toeboards onto the safety-catch
bolts.
➤
Fit the site-provided planks.
➤
Fix the planks with nails.
NOTICE
▪
Arrange the scaffold planking units either on
alternate sides from one 'storey' to the next,
or across the entire area.
▪
When the scaffold planking units are
located on alternate sides, 3 scaffold plank-
ing units must be used on the final (i.e. top)
‘storey’, one of them with a manhole. Make
sure that the manhole is in the correct posi-
tion here.
▪
If the load-bearing tower is over 6
m high,
back-stay it or combine it with other towers.
G
Scaffold planking
G
G
98003-259-01
Determining the right plank-length: Centre-to-
centre distance between the frames, minus
10
cm
A
Staxo 100 toeboard
B
Safety-catch bolt
C
Plank
Tr772-203-01
C
A
B
B