BioClass TR
18
- Check the flue is correctly installed using a condensation inspection tap and a draught
stabiliser.
- Check the hopper and the feed auger are correctly installed.
The feed auger must be
calibrated for a correct boiler functioning
(See
“Calibrating the feed auger”
). Check the right
type of fuel is being used.
- If the installation has flow and return valves, check they are open.
4.6
Installation delivery
After commissioning, the Technical Assistance Service will explain to the user how the boiler
functions, making any observations they consider relevant.
The installer is responsible for clearly explaining to the user the functioning of any control or
regulation device forming part of the installation but not supplied with the boiler.