Centrifugal Mist Collector, E-100 to EA-905
4
Site Selection
This collector can be located on a foundation or
structural framing.
Provide clearance from heat sources and avoid any
interference with utilities when selecting the location.
Rigging Instructions
Suggested Tools & Equipment
Clevis Pins and Clamps
Lifting Slings
Crane or Forklift
Pipe Sealant
Drift Pins
Pipe Wrenches
Drill and Drill Bits
Screwdrivers
End Wrenches
Socket Wrenches
Adjustable Wrench
Spreader Bars
Torque Wrench (inch/lbs, 9/16-in Socket)
Hoisting Information
Failure to lift the collector
correctly can result in severe
personal injury and/or property damage.
Use appropriate lifting equipment and adopt
all safety precautions needed for moving and
handling the equipment.
A crane or forklift is recommended for
unloading, assembly, and installation of the
collector.
Location must be clear of all obstructions, such
as utility lines or roof overhang.
Collector Location
Donaldson Torit equipment is not
designed to support site installed
ducts, interconnecting piping, or electrical
services. All ducts, piping, or electrical
services must be adequately supported to
prevent severe personal injury and/or property
damage.
When hazardous conditions or materials are
present, consult with local authorities for the
proper location of the collector.
Mist collection equipment may
reach peak sound pressure
levels above 80 dB (A). Noise levels should be
considered when selecting collector location.
Locate the collector to ensure easy access to electrical
connections, to simplify mist collection container
handling and routine maintenance, and to ensure the
straightest inlet and outlet ducts.
Check the Specification Control drawing for weight and
dimensions of the collector and components to ensure
adequate crane capacity.
Allow only qualified crane or forklift operators to lift the
equipment.
Refer to applicable OSHA regulations and local codes
when using cranes, forklifts, and other lifting equipment.
Lift collector and accessories separately and assemble
after collector is in place.
Use drift pins to align holes in section flanges during
assembly.