Prefilter Removal

1.  Remove the nylon mesh prefilter.
2.  Reinstall the prefilter placing the top edge against 

the upper end cap of the filter cartridge. Stretch the 

screen for a tight fit and secure using a hook-and-

loop fastener.

 

Note:  The prefilter must cover all holes in the 

perforated liner. Stretch to fit.

Filter Removal

1.  Disconnect electrical power.
2.  Open the bottom access door.
3.  Loosen four filter support knobs.
4.  Turn the retaining ring counterclockwise to release 

the ring and filter.

5.  Remove the retaining ring and filter and dispose of 

filter properly.

Instruct all personnel on safe use and maintenance 

procedures.

Use proper equipment and 

adopt all safety precautions 

needed for servicing equipment.  
Use appropriate access equipment and 

procedures. Note the standard collector is not 

equipped with access platforms unless noted 

on the specification drawings.
Electrical service or maintenance work must 

be performed by a qualified electrician and 

comply with all applicable national and local 

codes.
Turn power off and lock out all power before 

performing service or maintenance work.
Do not install in classified hazardous 

atmospheres without an enclosure rated for 

the application.

Maintenance Information

Operational Checklist

1.  Monitor the physical condition of the valve and auger 

and repair or replace any damaged components. 

 

Routine inspections will minimize downtime and 

maintain optimum system performance. This 

is particularly important on continuous-duty 

applications. 

2.  Monitor pressure drop across filters.
 

Abnormal changes in pressure drop may indicate a 

change in operating conditions and possibly a fault 

to be corrected.  

3.  Monitor exhaust.
4.  Monitor dust disposal.

Use proper safety and 

protective equipment when 

removing contaminants and filters.
Dirty filters may be heavier than they appear.
Use care when removing filters to avoid 

personal injury and/or property damage.
Turn power off and lock out all power before 

performing service or maintenance work.
Do not operate with missing or damaged filters.

Filter Removal and Installation

Summary of Contents for Vibra-Shake VS-1200

Page 1: ...owner Leave with the collector when set up and start up are complete Donaldson Company reserves the right to change design and specifications without prior notice Illustrations are for reference only...

Page 2: ...ach of these responsibilities are met As a manufacturer and supplier of Industrial Filtration Products Donaldson can assist process owners operators in the selection of filtration technologies However...

Page 3: ...ating and Specification Information 1 Operation 2 Inspection on Arrival 3 Installation Codes and Procedures 3 Installation 3 Foundations or Support Framing 3 Collector Location 4 Site Selection 4 Rigg...

Page 4: ...the cartridge acts as a cleanable secondary filter The Vibra Shake dust collectors standard features include an acoustic lined blower chamber and automatic filter cleaning Designed to increase the ver...

Page 5: ...ugh the center of the filter cartridge to the blower through the silencer and exits through the top clean air outlet Model VS is an intermittent duty collector which means that cleaning starts when th...

Page 6: ...remove shipping materials from the collector will compromise collector performance Inspect collector to ensure all hardware is properly installed and tight prior to operating collector The collector...

Page 7: ...nts to ensure adequate crane capacity Allow only qualified crane or forklift operators to lift the equipment Refer to applicable OSHA regulations and local codes when using cranes forklifts and other...

Page 8: ...air chambers and dust drawers Locate the collector as close to the dust source as possible except where explosive or flammable material exists Anchors must comply with local code requirements and mus...

Page 9: ...than baseplate hole diameter 3 Corrosive environment or outdoor installation may require stainless steel anchors 6 Position and bolt the cross brace in place using the hardware provided Do not tighte...

Page 10: ...e toward the outside of the bolt pattern 2 Lift the cabinet into position over the leg and hopper assembly and lower slowly Note Access the lifting lugs on VS 2400 and VS 3000 by removing the top cove...

Page 11: ...the fan motor and control box Use appropriate wire gauge for rated amp load as specified by local codes Electrical Wiring Electrical installation service or maintenance work must be performed by a qu...

Page 12: ...down time 60 second single shaker motor 180 second double shaker motor 3 60 second cleaning cycle 4 No time delay on start up If start up is initiated during the cleaning operation the shaker motor wi...

Page 13: ...rotation single phase power supply Follow manufacturer s instructions on the motor s nameplate To reverse rotation three phase power supply Switch any two leads on the motor junction box Do not look i...

Page 14: ...performed by a qualified electrician and comply with all applicable national and local codes Turn power off and lock out all power before performing service or maintenance work Do not install in class...

Page 15: ...gate is used close gate before servicing dust container Sharp edge of slide gate may result in personal injury while closing the slide gate Keep hands clear when operating the slide gate 4 Check integ...

Page 16: ...lange using 3 8 16 bolts washers and hex nuts 3 Attach the drum cover to the 55 gallon drum Optional Equipment 4 Use latches to secure the cover to the drum if equipped 5 Connect the flexible hose bet...

Page 17: ...hout Slide Gate 5 Gallon Pail Pack 1 Apply sealant to the hopper flange or the pail cover mounting plate flange toward the inside edge of the bolt pattern 2 Fasten the pail pack to the hopper using th...

Page 18: ...me 90 sec Single VS 550 1200 and 1500 Switches preset to OFF position Default set to 60 sec wait 60 sec clean ON 1 2 3 4 180 sec wait 30 sec clean 60 sec time 90 sec Double VS 2400 and 3000 Switch 1 t...

Page 19: ...aker spring cotter pin shaker bar shaker bolt jam nut Single and Double Shaker Assembly pressure switch low pressure port open to clean air chamber clean air chamber 3 16 in ID tubing connect to high...

Page 20: ...t do not stay running Incorrect motor starter installed Check for proper motor starter and replace if necessary Access doors are open or not closed tight Close and tighten access doors See Filter Inst...

Page 21: ...ation Collapsed or obstructed ductwork Remove and clean duct Replace collapsed duct Improper duct size or too much flexible duct Contact Donaldson Torit for assistance Collapsed or obstructed ductwork...

Page 22: ...timing sequence to start Check pressure switch adjustment if adjustable Turn screw clockwise until it stops and back out approximately three turns counterclockwise Faulty pressure switch With power to...

Page 23: ..._____________________________________________________________ Dust Properties Kst_______________Pmax______________MIE____________MEC_________________ Accessories_______________________________________...

Page 24: ...other costs expenses or damages whether direct indirect special incidental consequential or otherwise The terms of this warranty may be modified only by a special warranty document signed by a Direct...

Reviews: