5
Donaldson Company, Inc.
hopper
leg
cross
brace
inlet cover
hopper
leg
cross
brace
VS-550
VS-2400
Hopper and Leg Installation
2. Lift the hopper using a crane.
3. Stand each leg on its pad in position under hopper.
4. Use drift pins to align holes in the hopper with the
holes in the legs.
5. Secure legs to hopper using bolts, washers, and nuts
provided. Do not tighten hardware at this time. Do
not remove crane.
Standard Equipment
Dust Drawer Collectors
Standard equipment consists of a self-contained
collector housing the filters, blower, clean- and dirty-
air chambers, and dust drawers. Locate the collector
as close to the dust source as possible, except where
explosive or flammable material exists.
Anchors must comply with local
code requirements and must be
capable of supporting dead, live, wind, seismic,
and other applicable loads.
Anchor sizes shown are provisional, as final
anchor sizing will depend on jobsite load
conditions, collector location, foundation/
framing design variables and local codes.
Consult a qualified engineer for final selection
of anchors.
Hopper and Leg Installation
Reference Typical Foundation Anchor and leg assembly
drawing shipped with the collector prior to starting
assembly.
1. Prepare the foundation or support framing in the
selected location. Locate and install anchors.