INSTALLATION, USE AND MAINTENANCE
GBA-GBP-CBE-MBE SERIES
55
5.4 Deactivating at the end of work
To deactivate the crane at the end of work follow the instructions below:
1. Position the arm in a recovery position making sure of its stability and taking care that it does not
generate risks of collision or interferences with surrounding structures and/or machines
2. Release the lifting hook from the slings used to handle the load
3. Lift the hook, where possible, to a height not under 250 cm, i.e. so that it does not create disturbances
and danger for the movement of people and things below the crane.
If used with a manual hoist:
4. Make sure the manoeuvre chain does not generate risks of being drawn in
If used with a electric hoist:
4.
Stop all crane movements by pressing the “stop” button of the pushbutton panel
5.
Put the pushbutton panel in the “do not disturb” position
6.
Deactivate the power by putting the general switch in the “OFF” or “0” (zero) position.