5) Check the current position of the Z axis from
the "Machine Position" screen of the OP, and
enter the difference between current position
and "Z290." in the "parameter #1850 Z" field.
▪
To change the Z-axis grid shift parameter
Read the machine position (coordinates) displayed on the OP screen. Enter the
positive (+) parameter if the result of deducting "290." from the machine position is a
positive value; enter the negative (-) paramet
er in micron (μ) if the result is a negative
value. Add or deduct the above measurement to and from the existing parameter and
enter "INPUT", or enter the result plus the symbol, and press "+INPUT".
Add or deduct the above measurement to and from the existing parameter and enter
"INPUT", or enter the result plus the symbol, and press "+INPUT".
▪
Parameter for the Z-axis reference point: NO. #1850 Z
※
"Z290." Is the result where the test bar is 310mm long (L) and 60mm wide (D).
i.e.,
Z = L – (H - W + D/2),
Z = 310 – (750 - 700 + 30) = 290
▪
L : Length of the test bar: 310mm
If H is "Z0.", the distance between spindle gauge line and table center is: 750mm
W : W-axis stroke: 700mm
D : Diameter of the test bar: 60mm (D/2 = 30)
6) Return the Z axis to the reference point manually and repeat the instructions above until
the result falls below 0.005mm.
Summary of Contents for DBC 130 II
Page 1: ...Installation Manual DBC 130Ⅱ Machine Tools ...
Page 2: ......
Page 7: ...5 DBC 130II DBC130II ISE41 Ref 2 Right View Ref 3 Top View ...
Page 9: ...7 DBC 130II DBC130II ISE41 Ref 6 Top view of machine to install semi splash guard on Optional ...
Page 10: ...8 DBC 130II DBC130II ISE41 Ref 7 Top view of machine to install APC on Optional ...
Page 12: ...10 DBC 130II DBC130II ISE41 60 Tool Magazine ...
Page 60: ...58 DBC 130II DBC130II ISE41 Z axis ...
Page 121: ...119 DBC 130II DBC130II ISE41 19 Installation Complete ...