5. Installing the machine temporarily
5.1 Temporary installation of the column bed (Z-axis bed) assembly
1) Put final touches on the secondary mortar holes that were prepared for installing the
machine.
①
Clean up the inside of the holes.
②
Pour water into each hole and let the concrete soak up moisture.
※
Keep the concrete soaked in water for at least 12 hours before injecting grout,
and drain the water right before the injection. (If 30 days or more have passed
since constructing the foundation concrete, soak it in water for over 24 hours.)
This is to enhance the adhesiveness of the injected grout and to prevent the grout
from drying too quickly as well as to improve the fluidity of the grout.
22) Locate the foundation component box from the shipping package and prepare for
installation.
3) Adjust the level bolt on the level block so that it stands approximately 10 mm above the
distal end, and arrange the level plate, anchor and anchor bolt around the level bolt.
Approx
10mm
Summary of Contents for DBC 130 II
Page 1: ...Installation Manual DBC 130Ⅱ Machine Tools ...
Page 2: ......
Page 7: ...5 DBC 130II DBC130II ISE41 Ref 2 Right View Ref 3 Top View ...
Page 9: ...7 DBC 130II DBC130II ISE41 Ref 6 Top view of machine to install semi splash guard on Optional ...
Page 10: ...8 DBC 130II DBC130II ISE41 Ref 7 Top view of machine to install APC on Optional ...
Page 12: ...10 DBC 130II DBC130II ISE41 60 Tool Magazine ...
Page 60: ...58 DBC 130II DBC130II ISE41 Z axis ...
Page 121: ...119 DBC 130II DBC130II ISE41 19 Installation Complete ...