6.5 Curing the surface of grout
1) Keep supplying an adequate amount of water on the surface in the course of grout
curing.
▪
It is recommended that the surface be covered with a wet cloth to slow down moisture
evaporation.
2) Make a generous schedule for curing.
▪
The longer the curing period is, the greater the strength. Assign at least 5 days for
grout curing (7 days is recommended). Allow additional 2 or 3 days for curing in the
winter.
3) Keep vibrations, shocks and loads to a minimum level and maintain the ambient
temperature above 10
˚C for the curing period.
▪
When it is too low in temperature in the winter season, use a heater or hot blast stove
to maintain an appropriate temperature.
Summary of Contents for DBC 130 II
Page 1: ...Installation Manual DBC 130Ⅱ Machine Tools ...
Page 2: ......
Page 7: ...5 DBC 130II DBC130II ISE41 Ref 2 Right View Ref 3 Top View ...
Page 9: ...7 DBC 130II DBC130II ISE41 Ref 6 Top view of machine to install semi splash guard on Optional ...
Page 10: ...8 DBC 130II DBC130II ISE41 Ref 7 Top view of machine to install APC on Optional ...
Page 12: ...10 DBC 130II DBC130II ISE41 60 Tool Magazine ...
Page 60: ...58 DBC 130II DBC130II ISE41 Z axis ...
Page 121: ...119 DBC 130II DBC130II ISE41 19 Installation Complete ...