65
DBC 130II
DBC130II ISE41
※
Precautions on connection from air sources to machine
(1) Make sure the air pipeline from the site ceiling is bent upwards before running it
down to the machine. See the figures below. Do not run the pipeline to a side or
straight down to the machine. The pipeline will contain water inside, affecting the
performance of the machine.
However, if this happens, ask the installer to install the pipeline again as
instructed above.
(2) The pipeline from the site ceiling is then connected to the machine through a
distribution tank that filters the water generated from compressed air.
▪
It is advisable to use an air dryer such as the distribution tank.
3) Use an air hose or tube with an inner diameter
of at least 9 mm.
On-site air
pressure
Model
Ф
9
Hose
Band
Air
Hose
Summary of Contents for DBC 130 II
Page 1: ...Installation Manual DBC 130Ⅱ Machine Tools ...
Page 2: ......
Page 7: ...5 DBC 130II DBC130II ISE41 Ref 2 Right View Ref 3 Top View ...
Page 9: ...7 DBC 130II DBC130II ISE41 Ref 6 Top view of machine to install semi splash guard on Optional ...
Page 10: ...8 DBC 130II DBC130II ISE41 Ref 7 Top view of machine to install APC on Optional ...
Page 12: ...10 DBC 130II DBC130II ISE41 60 Tool Magazine ...
Page 60: ...58 DBC 130II DBC130II ISE41 Z axis ...
Page 121: ...119 DBC 130II DBC130II ISE41 19 Installation Complete ...