5-2
Time Required
Work
Procedures
Time Required
Equipment to be Used
Disassembly and
Loading on
Carrier
Counterweight Disassembly
25 min
Crane
Track Side Frame Disassembly
45 min
Crane
Front Disassembly
1 h 20 min
Crane
Sub Total
2 h 30 min
Reassembly
Front Assembly
2 h
Crane
Track Side Frame Assembly
1 h
Crane
Counterweight Assembly
1 h
Crane
Sub Total
4 h
Total Sum
6 h 30 min