16 Customer installed door jambs
16.1 Check jamb installation dimensions
CAUTION
Customer interface:
• Review jamb and door installation with
customer contact.
• Obtain any shop drawings.
• Are there any local code requirements?
Technician should be experienced in:
• Verifying jamb height and width between
jamb dimensions with shop or architect
drawings and with dormakaba installation
template.
• Insuring jambs are plumb, level, and
square.
16.1.1 Measure width between jambs.
1. Measure width between jambs at several points
vertically along jambs.
• Refer to Para. 14.1 for width between jambs
dimension.
• Measurement tolerance:
Width between jambs +1/8", -0"
16.1.2 Measure frame opening height.
1. Measure frame opening height along door opening.
• Minimum opening height:
Door header required door clearance.
16.1.3 Check jamb level and floor flatness.
1. Verify level between bottom of jambs
2. Check for floor high spots above jamb level.
Fig. 16.1.1 Door opening, jambs installed
Fig. 16.1.2 Checking floor high point
TIPS AND RECOMMENDATIONS
Reference Para. 14.3 and 14.4 for Program
Switch and RJ45 Panel cutout requirements.
Finished floor surface
Level
CAUTION
Any issues with floor high spots must be
resolved prior to installing header and door.
Width between jambs
Frame opening height
Customer jamb
Customer jamb
Finished floor surface
Finished floor surface