Planning information
Electrical
Only connect to the electricity supply when the device is
voltage-free.
electrical installation must be carried out by a professional
specialist, in accordance with VDe 0100. Please conform to
national statutory regulations, where different.
The installation of the connecting cable and concealed
rough parts for electronic control elements has to occur at
the same time that the pre-wall is closed.
Combine the devices only with original Dornbracht
components.
Space required for all components in the sub-distribution
board: approx. 500 x 500 mm (internal dimensions).
Space required for 3 fragrance modules: 1000 x 210 x 140
(overall dimensions). We recommend installation using xGrid
track art. no. 12 320 970 90
The fragrance modules and the power supply have to be
installed seperate from each other. The fragrance modules
must not be installed directly above the electrical
installation.
See page 16/17 for cable length and length of ductwork.
Part of the cable and tubing length is needed to make the
connections.
The maximum distance between fragrance modules and
ceiling installation enclosure for rain panel is 12 m.
The maximum vertical height between fragrance modules
and ceiling installation enclosure for rain panel is 4 m
and must not be exceeded.
Max. distance between the ceiling installation enclosure for
rain panel and the sub-distribution board: 12 m.
Max. distance between the fragrance modules and the
sub-distribution board: 1 m. Power supply cables can be
extended to max. 2 m on site.
The distance between the fragrance modules and the
closest heat source (e.g. steam generator, heating unit)
must not be less than 1 m.
The customer must provide the following circuit-breakers
and electrical components:
- earth leakage circuit breaker (30 mA, 2-pin, type A)
- Safety cut-out (6 A, type B).
- 3 x circuit breaker (16A, type 1S)
- equipotential bonding busbar in subdistribution board
- equipotential bonding (4 mm²) for concealed rough part
eValve (hand shower set)
The usage and the connection of equipotential bonding
(4 mm²) as shown on page 16 is mandatory. A mere con-
nection to metal piping is not permissable
Positioning
recommendations
Components
Zones of protection
Pre-wall installation