2.2 Installation requirements
Electrical supply:
Dispenser:
Length of the electical supply cable:
1.80m / 70.8in
Use a national adapter for the mains plug if
required
European 3-phase version:
The power supply cable has 5 cores, which
enables fixing a power supply plug for 3-phase
operation
•
•
•
Customer:
A grounded connection is required.
The mains connection must match the dispenser
output.
The dispenser must be protected individually.
Recommendation:
Use a fault current safety switch and an all poles
controlling contact breaking device.
European version:
When a fixed power supply is used for the
dispenser (not via mains plug), a separation
device with contact openings of at least 3 mm
for each pole must be installed. The ground
connection must be connectied tightly.
•
•
•
•
•
Water supply:
Dispenser:
Connections for hoses:
3/4“ - 5/8-18 UNF
National connection pieces are included in the
corresponding country kits
Install a water filter (delivered with the dispenser
for some countries)
Requirement for USA:
The dispenser must be installed with an
adequate return flow stop, which complies with
the legal regulations.
•
•
•
•
Customer:
Water supply line:
dynamic pressure of
min. 0.8 bar at 10 liters / minute -
min 11.6 psi at 2.6 USgal / minute
static pressure of max. 10 bar / 145 psi
temperature of max. 60°C / 140°F
Use a stop valve and a non return valve
•
-
-
-
•
Hot water connection:
For the connection of the dispenser to a hot
water supply (higher than 60°C / 140°F) a
hot water inlet valve must be installed in the
dispenser (option)
•
Hot water connection:
possible with a special inlet valve
temperature:
more than 60°C / 140°F, max. 75°C / 167°F
use only copper pipes
•
-
-
-
Additional cold water or café cool dispensing:
Install a pressure limiter or
a pre-cooling unit, which includes a pressure
limiter.
•
-
-
Additional cold water and café cool dispensing
an additional water supply line is required,
dynamic pressure of
min. 0.8 bar at 12 liters / minute -
min. 11.6 psi at 3.2 USgal / minute
•
-
-
ATTENTION:
Check the drinking water quality before installation, especially when
installing the cold water / café cool option or water tank for manual
filling. A drinking water filter should always be installed
When new water pipes are installed, flush them sufficiently before the
installation of the dispenser.
Read local regulations carefully, when you choose water suppy lines.
Use only neutral material with respect to taste,
•
•
Additional requirements:
Installation surface:
Walls and ceiling:
even, nonskid floor
dustfree and clean
Summary of Contents for Cafitesse 110
Page 2: ... 2009 Douwe Egberts Coffee Systems International DRAFT Version August 2009 D R A F T ...
Page 22: ...D R A F T Cafitesse 100 Next Generation Installation Putting into operation 2 20 August 2009 ...
Page 54: ...Cafitesse 100 Next Generation Programming 4 20 August 2009 ...
Page 58: ...D R A F T Cafitesse 100 Next Generation Functions Overview of assemblies 5 August 2009 ...
Page 71: ...Cafitesse 100 Next Generation Functions water system August 2009 5A 13 ...
Page 82: ...Cafitesse 100 Next Generation Functions dosing system 5C 10 August 2009 ...
Page 93: ......