Cafitesse 100 Next Generation
Functions - water system
5A-12
August 2009
Fig. 1
Fig. 3
Fig. 2
Remove the overflow hose (fig. 1).
Disconnect the plugs (1 to 3) of the heating
elements from the power supply and pull the ca-
bles upwards out of the dispenser (see chapter
A.2.5).
Undo the 2 flat connectors of the temperature
sensor and the cable connection of the level
sensor at the boiler lid (see chapter 2.4).
Remove the water inlet hose and take the cable
harness boiler out of the clamp at the boiler lid
(see chapter A.2.5).
ATTENTION:
Take care not to damage the
silicone hose during the dis-
assembly of the boiler.
Note:
Draw the hose out of the bottom
part of the machine so that it
doesn‘t get caught when lifting the
boiler out of the dispenser (fig. 2).
Pull the complete boiler together with the drain
tube upwards out of the housing and then place
it on a plane surface (fig. 3).
Note:
The reassembly is carried out in
reverse order.
•
•
•
•
•
Summary of Contents for Cafitesse 110
Page 2: ... 2009 Douwe Egberts Coffee Systems International DRAFT Version August 2009 D R A F T ...
Page 22: ...D R A F T Cafitesse 100 Next Generation Installation Putting into operation 2 20 August 2009 ...
Page 54: ...Cafitesse 100 Next Generation Programming 4 20 August 2009 ...
Page 58: ...D R A F T Cafitesse 100 Next Generation Functions Overview of assemblies 5 August 2009 ...
Page 71: ...Cafitesse 100 Next Generation Functions water system August 2009 5A 13 ...
Page 82: ...Cafitesse 100 Next Generation Functions dosing system 5C 10 August 2009 ...
Page 93: ......