TL 1128 (TOP HOLES)
Issued August 2016
Revision No: 006
Printed in U.S.A.
Copyright 2016, Bayne Premium Lift Systems
Actuator Assembly Instructions
20
7. Coat one end of the actuator tubes (3) ( Figure C-13 ) around the seal area with STP Oil Treatment as shown in
Figure C-7. Using a rubber mallet, drive the coated end of the tube onto the exposed rack until the tube end seats in
the actuator body, making sure that the seals remain in place as the tube enters the counter-bore. Repeat this
procedure for the other side.
Figure C-7
8. Install the six tie rod studs (6) ( Figure C-13 ) by screwing the short threaded end into the actuator body. Hand tighten
only at this time (the torque needed will be applied later in the procedure).
9. Place the tube cap (4) ( Figure C-13 ) on the table. Coat the sides of the two bores in the tube cap with STP Oil
Treatment. Install the cap over the tubes and rod studs with the oil port positioned to the left as shown in Figure C-
13. Using a rubber mallet, tap the tube cap over the tubes until the tubes seat in the cap, making sure that the seals
remain in place.
10.Place the tube mounting bracket (30) ( Figure C-13 ) over the two end rod studs opposite the oil port in the tube cap
as shown in Figure C-13.
11.Install the hex nuts (23) ( Figure C-13 ) and lock washers (24) on the tie rod studs. Torque the nuts to 50 ft-lb. in the
sequence shown in Figure C-8.
Figure C-8