6
|
Dresser Roots
removed before lubricating. If desired, VCI-10 may be
removed from within the cylinder shortly before start up
by spraying fine mist of petroleum solvent through the
blower while it is running at a slow speed with open inlet
and discharge, or it can remain in the blower if it is not
harmful to the operation of the connected system. VCI-
10 is a product of Daubert Chemical Co., Oak Brook, IL.
2. Paint shaft extension, inlet and discharge flanges, and
all other exposed surfaces with Nox-Rust X-110 or
equivalent.
3. Seal inlet, discharge, and vent openings. It is not
recommended that the unit be set in place, piped to the
system, and allowed to remain idle for extended periods.
If any part is left open to the atmosphere, the VCI-10
vapor will escape and lose its effectiveness.
4. Units are not to be subjected to excessive vibration
during storage.
5. Rotate drive shaft three or four revolutions every two
weeks.
6. Prior to start up, remove flange covers on both inlet and
discharge and inspect internal to insure absence of rust.
Check all internal clearances. Also, at this time, remove
gearbox and bearing covers and inspect gear teeth and
bearings for rust.
When ready to connect piping, remove main flange covers
and inspect blower interior for presence of foreign particles or
dirt adhering to machined surfaces. Clean out such material
by washing carefully with a petroleum solvent then rotate
impellers manually to make sure they turn freely. Also use
the same solvent to remove the anti-rust coating from flange
faces and any other surfaces.
Note:
interior cleaning is not
required if no dirt is found.
FOUNDATION
design depends on local soil conditions and
several other factors and can only be discussed generally
here. Additional information will be found in the publication
referred to at the beginning of this section. For satisfactory
operation of supported equipment, a concrete foundation
must be rigid, must have minimum defections, and must be
free from resonant frequencies in the operating speed range
of the equipment.
Length and width dimensions of the foundation should
provide at least 6 inches (150 mm) from any edge to the
nearest machine anchor bolt, as located from the certified
manufacturer’s general arrangement drawing. Depth
dimension should be determined by design, but a minimum
practical depth is considered to be twice the distance
between shaft centers (or gear diameter) of the unit, or
sufficient depth to attain a concrete mass a minimum of 1-1/2
times the weight of the blower and motor. The concrete
block should be permitted to cure for a minimum of 28 days
before the blower is grouted in place. Any block distortions
during curing then will have little or no affect on equipment
and alignment. To simplify machine leveling and provide good
grouting bond, the top of the foundation should be struck-off
as level as possible but left with a rough surface.
Spring-type vibration isolating mounting are
not recommended
for use directly between the operating equipment and the
foundation. Where such mountings are required, they should
be designed to carry a reinforced concrete slab on which the
equipment is mounted. This slab must have good rigidity against
bending and twisting, and the suspension system will require
careful adjustment to produce a reasonably level condition
during operation. All piping will require flexible sections and
supports to reduce connection strains on the unit to a minimum.
Direct use of structural framing members for mounting
is not
recommended
. If unavoidable, it should be restricted to
units of the smaller frame sizes, and spring-type mountings
should not be used. Structural members must be rigid, and
will probably require reinforcement if part of a building. Noise
transmission can be reduced by use of a cork isolating pad.
This can be 1 to 2 inch (25-50 mm) thickness, bedding on
a full steel plate attached to the structure and carrying rigid
concrete slab on which the equipment is mounted.
ANCHOR BOLTS
are to be placed within the foundation
forms before concrete is poured. Foundation bolts installed
as shown in Figure 2, with diameter and length as in Table 2
are recommended. The bolts must be located as accurately
as possible from dimensions on certified installation drawing.
To obtain a bolt location tolerance of 1/8" (3mm), use of
drilled templates firmly secured to the foundation forms is
recommended.
The bolt sleeves shown, if kept centered around the bolts
and free of concrete, will allow bolts to be sprung enough to
correct for small variations in bolt setting and machine drilling.
The sleeves are filled in the final grouting operation. Bolt
positions should be adjusted vertically so that the top ends
will extend at least 1-1/2 diameters above the soleplate or
taper washer, or as shown on the installation drawing.
Jack screws are provided to make leveling the height adjust-
ments easier. Steel plates, approximately 4" x 4" x 1/2 " (100 x
100 x 13 mm) should be placed on the foundation under each
jack screw location. Plates and anchor bolts are not furnished
as standard accessories.
LEVELING
is very important and should be performed with
care, using a good machinists level having a ground glass
bubble vial. A setting as level as possible in all directions is
the result to be worked toward. Blowers should be leveled
from drive shaft and pipe flanges. Machined baseplates
have pads running in both length and width directions. On
Figure 2 - Typical Anchor Bolt Detail
Summary of Contents for Roots DVJ WHISPAIR
Page 22: ...DVJ WHISPAIR Dry Exhauster 23 Figure 15 Assembly of 10 thru 12 DVJ V V Belt Drive Splash Lube ...
Page 23: ...24 Dresser Roots Figure 16 Sectional Assembly of 10 thru 14 DVJ V Blowers ...
Page 24: ...DVJ WHISPAIR Dry Exhauster 25 Figure 17 Sectional Assembly of 16 20 DVJ Common Lube ...
Page 25: ...26 Dresser Roots Figure 18 Sectional Assembly of 1016 DVJ V Units ...