Fig. 4.33. Dumping Into Truck
Put enough loose rock or dirt into the truck first to act as cushioning material before proceeding to
load larger rocks (Figure 4.34.)
Fig. 4.34. Dumping Large Rocks Into Truck
After the bucket empties, move the bucket control lever back into the rollback position. The lever will
be maintained in this detached position by the solenoid latch. If the bucket is clear off the truck body,
back the loader way from the truck, lower the boom and return to the loading site. The bucket will
automatically return to its pre-set working position.
Lower loaded or unloaded bucket to the ground when waiting for any length of time.
WARNING! Never travel with an unstable and solid rock.
4.19.2. DIGGING, CLEARING AND LEVELING
When digging or excavating lower the bucket to the ground. Adjust the angle of the cutting edge
when the machines moves forward, Fig. 4.35. Change inclination of the angle of the cutting edge
and cutting edge depth using boom and bucket control levers depending on bucket filling. Establish
the parameters to obtain the best bucket filling. When the bucket is full, roll it back and raise it clear
off the ground and carry the load to the desired dump area.
Summary of Contents for 560C
Page 1: ...OM560C99 1E OPERATOR S MANUAL 560C SERIAL NUMBERS 15001 AND UP ...
Page 3: ......
Page 5: ......
Page 7: ......
Page 10: ...SECTION 1 INTRODUCTION ...
Page 12: ......
Page 16: ...SECTION 2 SAFETY PRECAUTIONS ...
Page 18: ......
Page 32: ...SECTION 3 MACHINE TRANSPORT AND STORAGE ...
Page 34: ......
Page 42: ...SECTION 4 OPERATING ...
Page 43: ......
Page 45: ......
Page 49: ...SECTION 4 OPERATING Page 6 OM560C99 1E DRESSTA UNIVERSAL SYMBOLS FOR INSTRUMENTS AND CONTROLS ...
Page 88: ...SECTION 5 MAINTENANCE ...
Page 141: ...SECTION 6 SPECIFICATIONS ...
Page 143: ......