DOC-0128 Rev F
© 2017 DROPLET MEASUREMENT TECHNOLOGIES
1 0
6)
If desired, mount the touch screen to the front of the CCN case:
a.
Remove the instrument’s front cover. There will be 12 screws around the perimeter
of the instrument, and three on the left side into the connection panel. Once these
screws are removed, the instrument cover can be lifted off.
b.
Remove the two Phillips-head screws that hold the tripod leg to the back of the
screen. This will expose the back of the screen and the location of the four mounting
holes.
c.
Remove the four hole plugs from the front of CCN case.
d.
Connect the cables to the screen.
e.
Mount the screen to the case, using the four 4.7 mm screws with lock washers that
are provided in the startup kit.
f.
Save the parts that were removed from the screen and the case.
g.
Put the cover back on the instrument.
7)
Connect the touch-screen video and serial cables to the side panel. Turn on power to the
touch screen either from the external power supply or from the side panel, using the cable
provided.
8)
Remove plugs from inlet and outlet fitting on the side of the unit.
9)
Proceed to the following section.
Figure 2: Bottle Hold-Down Clamp